PV System Disconnect: Max Number, Ratings, and Allowed Types
NEC 690.13(C) A PV system disconnect can use up to six switches or breakers, must be rated for the system's max current, fault current, and voltage, and must be a lockable, simultaneous-disconnect type from an approved list.
Q1 NEC 690.13(C)
An installer wants a single PV system disconnecting means to cover the combined ac output of four microinverters using individual breakers. Is this permitted?
- A No, only one breaker per disconnecting means is allowed for inverter output
- B Yes, up to six switches or sets of circuit breakers may combine into one disconnecting means
- C No, ac modules and inverters must each have a separate disconnecting means
- D Yes, but only if all four breakers are in separate enclosures on different walls
Show answer & explanation
Correct: B — Yes, up to six switches or sets of circuit breakers may combine into one disconnecting means
Per 690.13(C), a PV system disconnecting means can consist of up to six switches or sets of circuit breakers, mounted in a single enclosure or a group of enclosures, and a single disconnecting means is permitted for the combined ac output of one or more inverters or ac modules. There's no rule limiting it to one breaker, no requirement to separate ac modules and inverters, and no requirement about enclosures being on different walls.
Calculating Maximum Circuit Current
NEC 690.8(A) Every PV circuit type has one required method for maximum current: 125% of summed short-circuit ratings for source circuits, summed rated outputs for converters and inverters, or rated input current for converter input circuits.
Q2 NEC 690.8(A)
Per 690.8(A)(1)(a), what is the standard method for determining maximum current on a photovoltaic source circuit?
- A Use 70 percent of the module nameplate operating current
- B Use the inverter's continuous output current rating
- C Sum the parallel module short-circuit current ratings and multiply by 125 percent
- D Sum the parallel module short-circuit current ratings with no multiplier
Show answer & explanation
Correct: C — Sum the parallel module short-circuit current ratings and multiply by 125 percent
690.8(A)(1)(a)(1) requires summing the short-circuit current ratings of parallel-connected PV modules and applying a 125% multiplier. The inverter continuous output rating is the method for inverter output circuits, not source circuits, under 690.8(A)(1)(c). Omitting the multiplier or substituting a 70% factor doesn't match the required calculation.
Disconnecting Means for Isolating PV Equipment
NEC 690.15 PV equipment needs a way to isolate it from ungrounded conductors, and that means is either a full equipment disconnect or, on low-current circuits, a simpler isolating device.
Q3 NEC 690.15
A PV inverter circuit operates at a maximum circuit current of 25 amperes. Which disconnecting option is permitted that would NOT be permitted if the circuit carried 40 amperes?
- A A lockable disconnect located out of sight from the equipment
- B An isolating device without an interrupting rating, marked "Do Not Disconnect Under Load"
- C A disconnect that simultaneously opens all ungrounded conductors
- D An equipment disconnecting means rated for the available fault current
Show answer & explanation
Correct: B — An isolating device without an interrupting rating, marked "Do Not Disconnect Under Load"
690.15(A)(3) permits an isolating device per 690.15(B) only where the maximum circuit current is 30 amperes or less; at 25 A this is available, but at 40 A only an equipment disconnecting means under 690.15(C) qualifies. The equipment disconnecting means, simultaneous-disconnect, and lockable-disconnect options all describe 690.15(C) equipment disconnects, which remain valid at any current level, so they aren't the answer that's uniquely unlocked by the lower current.
DC circuit wiring methods and labeling inside buildings
NEC 690.31(D) Inside buildings, PV dc circuits over 30 volts or 8 amperes must run in metal raceway, listed MC cable, or metal enclosures, and every exposed run or box must carry a red-and-white PV warning label.
Q4 NEC 690.31(D)
A PV system dc circuit inside a building operates at 45 volts and 10 amperes. Which wiring method satisfies 690.31(D)(1)?
- A Type NM cable
- B Open cable tray with nonmetallic cable, since the run is fully exposed and visible
- C PVC conduit with no metal enclosure
- D Electrical metallic tubing (metal raceway)
Show answer & explanation
Correct: D — Electrical metallic tubing (metal raceway)
Since this circuit exceeds 30 volts and 8 amperes, 690.31(D)(1) requires metal raceway, metal enclosures, or Type MC cable meeting 250.118(A)(10)(b) or (c). Metallic tubing qualifies as metal raceway. Type NM cable and plain PVC or nonmetallic cable trays don't provide the required metal containment, and being exposed doesn't exempt a circuit from this requirement.
DC ground-fault detector-interrupter (GFDI) protection requirement
NEC 690.41(B) PV dc circuits over 30 V or 8 A need listed GFDI protection that disconnects the faulted circuit and gives visible indication of the fault.
Q5 NEC 690.41(B)
A PV source circuit is solidly grounded, has only two modules in parallel, and is mounted on a ground-mounted rack away from any structure. Under 690.41(B), is GFDI protection required?
- A No, because GFDI is only required on circuits located on or in a building
- B No, because it meets the solidly grounded, two-module, not-on-a-building exception
- C Yes, because any circuit exceeding 8 amperes always requires GFDI regardless of grounding
- D Yes, because GFDI is required on every PV source circuit without exception
Show answer & explanation
Correct: B — No, because it meets the solidly grounded, two-module, not-on-a-building exception
690.41(B) permits solidly grounded PV source circuits with not more than two modules in parallel and not on or in buildings to skip GFDI protection. The other options misstate the exception — GFDI is otherwise required above 30 V or 8 A, and being off a building alone (without solid grounding and the two-module limit) doesn't create the exception.
Maximum Voltage Limits by Installation Location
NEC 690.7 PV dc circuit voltage is capped at 600 V in one- and two-family dwellings and 1000 V for other buildings, measured as the highest voltage between any two conductors or a conductor and ground.
Q6 NEC 690.7
A PV array is mounted on the roof of a single-family home, with dc circuits running into the attic to an inverter. What is the maximum allowable dc voltage for these circuits?
- A 1500 volts
- B 1000 volts
- C 300 volts
- D 600 volts
Show answer & explanation
Correct: D — 600 volts
Per 690.7(2), PV system dc circuits on or in one- and two-family dwellings shall not exceed 600 volts. The 1000-volt figure applies to arrays on other building types or dc circuits inside buildings generally, not one- and two-family dwellings.
Mating connector safety requirements (polarity, guarding, locking, interrupt rating)
NEC 690.33 PV mating connectors must be polarized, non-interchangeable with other systems, guarded, locking, and rated to safely interrupt current — or clearly marked if they aren't.
Q7 NEC 690.33
A readily accessible PV mating connector operates at 40 volts dc. Per 690.33(C), what does this require?
- A A tool for opening the connector
- B No special requirement, since 40 volts dc is below the 50-volt hazardous threshold
- C A tool for opening only if the connector is also rated to interrupt current
- D Listing for intermatability, regardless of brand matching
Show answer & explanation
Correct: A — A tool for opening the connector
690.33(C) sets the tool-to-open threshold at over 30 volts dc (or 15 volts ac) for readily accessible connectors, not 50 volts. At 40 Vdc and readily accessible, a tool is required for opening, independent of the connector's current-interrupting rating. Intermatability listing is only required when connectors are not identical type and brand.
Overcurrent Device Ratings (125% Rule)
NEC 690.9(B) PV overcurrent devices must be listed for PV use and sized at not less than 125% of the calculated current, unless the assembly is listed for 100% continuous operation.
Q8 NEC 690.9(B)
Per 690.9(B), what is required of overcurrent devices used in PV source circuits?
- A They must be rated exactly 100% of the calculated current with no rounding
- B They must be located outdoors within sight of the array
- C They must be inverse-time circuit breakers only, never fuses
- D They must be listed for use in PV systems
Show answer & explanation
Correct: D — They must be listed for use in PV systems
690.9(B) requires overcurrent devices used in PV source circuits to be listed for use in PV systems. There's no exact-100%-with-no-rounding rule, no breaker-only restriction, and no outdoor-location requirement in this section.
When Overcurrent Protection Is Required
NEC 690.9(A) PV circuits skip overcurrent protection only when conductor ampacity already covers the worst-case combined current; otherwise OCPD goes at the high-current end, or on both ends if the circuit doesn't qualify for an exception.
Q9 NEC 690.9(A)
Under 690.9(A)(1), overcurrent protective devices are not required on a PV circuit when which set of conditions is met?
- A The conductors have sufficient ampacity for the maximum circuit current, and combined source currents do not exceed the max OCPD rating for the module or converter
- B The circuit is protected from overcurrent at one end only
- C The circuit is shorter than 3 m (10 ft) and terminates outside a building
- D The conductors are installed in a metal raceway for their entire length
Show answer & explanation
Correct: A — The conductors have sufficient ampacity for the maximum circuit current, and combined source currents do not exceed the max OCPD rating for the module or converter
690.9(A)(1) requires both conditions: sufficient conductor ampacity for maximum circuit current, and combined source current not exceeding the maximum OCPD rating specified for the PV module or electronic power converter. The raceway and one-end options are conditions from 690.9(A)(3)'s exceptions, not the no-OCPD-needed path, and neither is sufficient by itself.
Restrictions on PV DC systems over 1000 volts
NEC 690.31(G) PV dc circuits over 1000 volts are banned from dwellings and any building with habitable rooms, and exterior equipment must stay low and close.
Q10 NEC 690.31(G)
Under 690.31(G), which installation is explicitly prohibited for PV dc circuits with a maximum voltage greater than 1000 volts?
- A Installation on or in a one- and two-family dwelling
- B Installation on the exterior of a detached industrial building
- C Installation in an outdoor, ground-mounted utility-scale array
- D Installation on a commercial building exterior at 9 ft above grade
Show answer & explanation
Correct: A — Installation on or in a one- and two-family dwelling
690.31(G)(1) flatly bans this equipment on or in one- and two-family dwellings. A detached industrial building and a ground-mounted array aren't dwellings or habitable-room buildings, so they aren't banned outright, and 9 ft above grade actually satisfies the 'less than 10 ft' exterior placement rule rather than violating it.
Installing single-conductor PV cable outdoors and in cable trays
NEC 690.31(C)(1) Exposed single-conductor PV cable must be PV wire or sunlight-resistant USE-2/RHW-2, secured every 24 in. at 8 AWG or smaller and every 54 in. above that; in cable tray it's supported every 12 in. and secured every 54 in.
Q11 NEC 690.31(C)(1)
A 10 AWG single-conductor cable is installed exposed outdoors within a PV array dc circuit, not in a cable tray. What is the maximum allowed interval between securement points?
- A 1800 mm (72 in.)
- B 1400 mm (54 in.)
- C 300 mm (12 in.)
- D 600 mm (24 in.)
Show answer & explanation
Correct: D — 600 mm (24 in.)
Per 690.31(C)(1)(b), exposed cables sized 8 AWG or smaller must be supported and secured at intervals not exceeding 600 mm (24 in.). The 1400 mm (54 in.) spacing applies only to exposed cables larger than 8 AWG under 690.31(C)(1)(c), and 300 mm (12 in.) is the cable tray support interval under 690.31(C)(2), not the exposed-cable interval.
Calculating Max Voltage for PV Source Circuits
NEC 690.7(A) Cold weather raises PV open-circuit voltage, so string voltage must be calculated at the lowest expected ambient temperature, not rated Voc.
Q12 NEC 690.7(A)
Why must a designer correct a PV source circuit's open-circuit voltage for the lowest expected ambient temperature rather than use the module's rated Voc directly?
- A Rated Voc already includes a cold-weather safety margin required by the manufacturer
- B Open-circuit voltage increases as temperature drops, so cold weather produces the highest system voltage
- C Temperature only affects current output, not voltage, so correction is a conservative extra step
- D Open-circuit voltage decreases as temperature drops, so warm-day Voc is the worst case
Show answer & explanation
Correct: B — Open-circuit voltage increases as temperature drops, so cold weather produces the highest system voltage
Per 690.7(A), PV open-circuit voltage rises as ambient temperature falls, so the coldest expected temperature at the site produces the maximum system voltage — that's why the correction is required. The claim that voltage decreases in cold weather has it backwards, and temperature does affect voltage (not just current), so those distractors misstate the underlying physics behind 690.7(A).
PV System Disconnecting Means: Purpose, Location, and Marking
NEC 690.13 The PV disconnect must be readily accessible, and if line and load terminals can stay energized when open, it needs a shock-hazard warning label.
Q13 NEC 690.13
A PV system disconnecting means operates at 48 V and is readily accessible to unqualified persons. Its enclosure has a hinged cover that exposes energized parts when opened. What does 690.13(A)(2) require?
- A No additional cover requirement applies below 50 V
- B The cover must be permanently welded shut after installation
- C The cover must be locked or require a tool to open
- D The disconnect must be relocated to a non-accessible area instead
Show answer & explanation
Correct: C — The cover must be locked or require a tool to open
Per 690.13(A)(2), when a disconnecting means for circuits above 30 V is readily accessible to unqualified persons, any enclosure door or hinged cover exposing energized parts when open must be locked or require a tool to open. The 48 V system is above the 30 V threshold, so the locked-or-tool-required cover option applies; there's no exemption at 50 V, and welding shut or relocating away from readily accessible are not what the rule calls for.
Rapid Shutdown Initiation Devices
NEC 690.12(C) A rapid shutdown initiation device must be readily accessible, clearly marked, and — with multiple PV systems on one service — capped at six switches or breakers.
Q14 NEC 690.12(C)
Under 690.12(C), where must the rapid shutdown initiation device be located for a one-family dwelling?
- A Inside the main electrical room, behind the service panel
- B Anywhere on the property, provided it is labeled
- C A readily accessible outdoor location
- D Inside the dwelling near the utility meter only
Show answer & explanation
Correct: C — A readily accessible outdoor location
690.12(C) specifically requires that for one- and two-family dwellings, the initiation device be located at a readily accessible outdoor location — not merely somewhere labeled or indoors near equipment.
Rapid Shutdown Scope & Controlled Conductors
NEC 690.12 PV circuits on or in buildings need rapid shutdown, and controlled conductors mean PV dc circuits plus inverter output circuits from inverters inside the array boundary.
Q15 NEC 690.12
Which PV installation is NOT required to comply with the rapid shutdown requirements of 690.12?
- A A rooftop PV array on a detached garage used for storage
- B A ground-mounted PV system whose circuits enter a building used solely to house PV equipment
- C A rooftop PV array on an occupied dwelling
- D A rooftop PV array on a commercial building with an accessible roof
Show answer & explanation
Correct: B — A ground-mounted PV system whose circuits enter a building used solely to house PV equipment
690.12 exempts ground-mounted PV system circuits that enter buildings whose sole purpose is to house PV system equipment. Rooftop arrays on occupied or general-use buildings, including a storage garage, still fall under the general rapid shutdown requirement since that exemption applies only to nonenclosed detached structures like carports and trellises, not enclosed storage buildings.
Rapid Shutdown Voltage Limits Inside/Outside the Array
NEC 690.12(B) Within 30 seconds of initiation, controlled conductors must drop to 30V outside the array boundary and to 80V (or use a listed PVHCS) inside it.
Q16 NEC 690.12(B)
Under 690.12(B), how is the 'array boundary' defined?
- A 305 mm (1 ft) measured only from the point of entry into a building
- B 1 m (3 ft) from the array in all directions
- C 1 m (3 ft) from the point of entry inside a building
- D 305 mm (1 ft) from the array in all directions
Show answer & explanation
Correct: D — 305 mm (1 ft) from the array in all directions
690.12(B) defines the array boundary as 305 mm (1 ft) from the array in all directions. The 1 m (3 ft) distance is a separate measurement used in 690.12(B)(1) for conductors inside a building, not the array boundary itself.
AC modules and AC module systems (source vs. output circuits)
NEC 690.6 An ac module's built-in inverter makes its PV source circuit internal and exempt from Article 690 source-circuit rules — only its output, treated as an inverter output circuit, is regulated.
Q17 NEC 690.6
Per 690.6(A), how are the PV source circuit conductors and inverter inside an ac module treated?
- A As a feeder circuit requiring a dedicated disconnecting means
- B As a standard PV source circuit subject to the same sizing and disconnect rules as a string-inverter system
- C As an inverter output circuit
- D As internal components of the ac module, exempt from Article 690's PV source circuit requirements
Show answer & explanation
Correct: D — As internal components of the ac module, exempt from Article 690's PV source circuit requirements
690.6(A) states that Article 690's PV source circuit requirements do not apply to ac modules — the source circuit, conductors, and inverter are internal components of the module. The inverter output circuit classification and standard PV source-circuit treatment both describe wiring outside this exemption.
DC Arc-Fault Circuit Protection
NEC 690.11 PV dc circuits at 80 V or more between any two conductors need listed arc-fault protection unless the wiring method itself is metal-enclosed and meets a location exception.
Q18 NEC 690.11
Under 690.11, PV system dc arc-fault circuit protection is required when the dc circuit operates at what voltage between any two conductors?
- A 150 volts dc or greater
- B 100 volts dc or greater
- C 80 volts dc or greater
- D 50 volts dc or greater
Show answer & explanation
Correct: C — 80 volts dc or greater
690.11 sets the threshold at 80 volts dc or greater between any two conductors. The 50 V, 100 V, and 150 V thresholds are all voltage levels used elsewhere in Article 690 (such as rapid shutdown or grounding rules), not the arc-fault protection trigger, so they are plausible but incorrect here.
Sizing Conductor Ampacity from Max Current
NEC 690.8(B) PV circuit conductors must meet the larger of two ampacities: max current × 125%, or max current with real-world adjustment and correction factors applied.
Q19 NEC 690.8(B)
Per 690.8(B), how is the required ampacity of a PV source or output circuit conductor determined?
- A Always the maximum current multiplied by 125%, regardless of installation conditions
- B The maximum current with adjustment and correction factors only, since it already accounts for continuous operation
- C The smaller of the two calculated values, to avoid oversizing the conductor
- D The larger of the 125%-of-max-current value or the max current with adjustment and correction factors applied
Show answer & explanation
Correct: D — The larger of the 125%-of-max-current value or the max current with adjustment and correction factors applied
690.8(B) requires the ampacity to be not less than the larger of 690.8(B)(1) (max current × 125%) or 690.8(B)(2) (max current with adjustment and correction factors). Using only the 125% value or only the adjustment/correction value ignores the rule's 'larger of' comparison, and picking the smaller value would undersize the conductor.
Allowed PV DC circuit grounding configurations
NEC 690.41(A) PV dc circuits no longer default to solidly grounded — 690.41(A) lists six acceptable schemes, and most modern inverters run ungrounded or functionally grounded.
Q20 NEC 690.41(A)
Under 690.41(A), which of the following is NOT one of the permitted PV system dc circuit grounding configurations?
- A Ungrounded circuits
- B A 3-wire circuit with both outer conductors solidly grounded
- C Circuits protected by equipment listed and identified for the use
- D 2-wire circuits with one functionally grounded conductor
Show answer & explanation
Correct: B — A 3-wire circuit with both outer conductors solidly grounded
690.41(A) lists six configurations: functionally grounded 2-wire, bipolar with a center-tap reference, circuits not isolated from a grounded inverter output, ungrounded circuits, solidly grounded circuits (as permitted in 690.41(B), not with both outer conductors grounded), and circuits protected by listed and identified equipment. Grounding both outer conductors of a 3-wire circuit isn't one of the recognized schemes.
Grouping and identifying PV DC circuits with other systems
NEC 690.31(B) PV dc circuits can't share an enclosure or raceway with other systems unless separated by a barrier, insulated for the highest voltage present, or in listed jacketed/metal-clad cable — and mixed ac/dc conductors must be grouped every 6 ft.
Q21 NEC 690.31(B)
PV system dc circuits are installed in the same pull box as inverter output circuits with no physical barrier between them. Under what condition is this permitted?
- A All conductors in the box have an insulation rating at least equal to the maximum circuit voltage present, and identification/grouping rules are met
- B Only if the inverter output circuit is rated 30 A or less
- C Only if the PV dc conductors are run in a separate conduit sleeve inside the box
- D Never — a barrier is always mandatory when dc and inverter output circuits share an enclosure
Show answer & explanation
Correct: A — All conductors in the box have an insulation rating at least equal to the maximum circuit voltage present, and identification/grouping rules are met
690.31(B)(1) allows PV dc circuits and inverter output circuits to share a junction box, pull box, or wireway without a barrier as long as all conductors carry an insulation rating equal to at least the highest circuit voltage present, and the dc conductors are identified and grouped per 690.31(B)(2) and (B)(3). A barrier is only one of the two permitted paths, not an absolute requirement, and current rating of the inverter circuit isn't the deciding factor.
Flexible cords/cables for tracking arrays and small-conductor module interconnects
NEC 690.31(C)(4) Cords on tracking PV arrays must be hard service/extra-hard usage cord rated for outdoor sun and water exposure, and 16-18 AWG module interconnects need their own listing and ampacity check.
Q22 NEC 690.31(C)(4)
An installer is wiring the moving portion of a single-axis tracking PV array. Which cord type satisfies 690.31(C)(4)?
- A Standard building wire in flexible metal conduit
- B SPT-2 lamp cord rated for dry locations
- C Junior hard service cord rated for damp locations only
- D Hard service cord rated extra-hard usage, listed for outdoor use, water resistant, and sunlight resistant
Show answer & explanation
Correct: D — Hard service cord rated extra-hard usage, listed for outdoor use, water resistant, and sunlight resistant
690.31(C)(4) requires flexible cords on moving parts of tracking arrays to be a hard service cord or portable power cable suitable for extra-hard usage, listed for outdoor use, water resistant, and sunlight resistant. Junior hard service cord and lamp cord fall short of the extra-hard-usage rating, and building wire in flexible metal conduit is not a flexible cord/cable assembly covered by this rule.
Connecting the PV array to a grounding electrode system
NEC 690.47(A) PV array equipment grounding conductors always land on the building's grounding electrode system per Part VII of Article 250, separate from any other bonding requirement.
Q23 NEC 690.47(A) Code lookup
A ground-mounted PV array's equipment grounding conductors need to be connected to a grounding electrode system. Which section requires this connection and directs you to Part VII of Article 250 for how to make it?
- A 690.47(B)
- B 690.43(C)
- C 690.45
- D 690.47(A)
Show answer & explanation
Correct: D — 690.47(A)
690.47(A) requires PV array equipment grounding conductors to connect to a grounding electrode system per Part VII of Article 250, in addition to any equipment grounding conductor requirements of 690.43(C). 690.47(B) instead specifies which electrodes and GEC sizing are permitted, and 690.45 only covers EGC sizing, not the grounding electrode connection itself.
Selecting grounding electrodes and sizing the GEC for PV arrays
NEC 690.47(B) A PV array's grounding electrode conductor is sized off Table 250.66, and the array's own structure can often serve as the electrode.
Q24 NEC 690.47(B) Code lookup
A ground-mounted PV array's metal support structure drives into the earth deep enough to meet 250.52 requirements, and the installer wants to use that structure itself as the system's grounding electrode instead of driving a separate rod. Which section permits using the support structure as the grounding electrode?
- A 690.47(A)
- B 690.43(B)
- C 690.47(B)
- D 690.45
Show answer & explanation
Correct: C — 690.47(B)
690.47(B) is the Grounding Electrodes and Grounding Electrode Conductors section, and it specifically states a ground-mount support structure can serve as the grounding electrode if it meets 250.52. 690.47(A) covers buildings/structures supporting a PV system, a different scenario, and 690.45 sizes equipment grounding conductors, not the grounding electrode conductor.
Bonding PV module frames via mounting systems and grounded supports
NEC 690.43(A) PV module frames must bond back to the equipment grounding conductor, and any mounting hardware or metal support used to do that job must be listed and identified for bonding — not just conductive.
Q25 NEC 690.43(A)
An installer plans to use the aluminum racking rail itself, with standard non-listed clamps, as the bonding path for PV module frames. Is this permitted under 690.43(A)?
- A No, mounting devices used for bonding must be listed, labeled, and identified for bonding PV modules
- B No, module frames may never be bonded through mounting hardware
- C Yes, any continuous metal racking system provides an acceptable bonding path
- D Yes, as long as the system operates below 50 volts
Show answer & explanation
Correct: A — No, mounting devices used for bonding must be listed, labeled, and identified for bonding PV modules
690.43(A) requires that devices and systems used both for mounting and for bonding module frames be listed, labeled, and identified for bonding PV modules (per UL 2703). A generic conductive rail with non-listed clamps doesn't satisfy this, voltage is irrelevant under 690.43, and mounting hardware CAN serve as the bonding path when properly listed — so the 'never' option is also wrong.
Installing multiconductor jacketed PV/DG cable
NEC 690.31(C)(3) Multiconductor jacketed PV/DG cable follows its listing (or assembly instructions), needs a raceway inside buildings other than rooftops, and outside a raceway must be sunlight resistant, protected, and secured every 6 ft and within 24 in of connectors.
Q26 NEC 690.31(C)(3) Code lookup
A rooftop PV array on a commercial building uses multiconductor jacketed DC source-circuit cable (not part of a listed PV wiring assembly). Away from the raceway-required run, the cable is installed exposed on the rooftop, closely following the racking support structure. Which section specifies how far apart this cable must be secured to the support structure?
- A 690.31(C)(3)
- B 690.31(C)(4)
- C 690.31(C)(1)
- D 690.31(C)(2)
Show answer & explanation
Correct: A — 690.31(C)(3)
690.31(C)(3) is the multiconductor jacketed cable rule and lists the 1.8 m (6 ft) securing interval for cable run outside a raceway, closely following support structures. 690.31(C)(1) governs single-conductor cable and 690.31(C)(4) governs flexible cords/cables to tracking arrays, neither of which fits jacketed multiconductor cable on fixed racking; 690.31(C)(2) covers cable tray installations, not exposed surface-mounted runs.
General wiring methods and raceway types allowed for PV circuits
NEC 690.31(A) Any Code-recognized raceway or cable works for PV circuits, but source and output circuits over 30 volts in readily accessible spots must be guarded or run in Type MC cable, jacketed multiconductor cable, or raceway.
Q27 NEC 690.31(A)
A PV source circuit operates at 60 volts dc and runs through a readily accessible mechanical room where unqualified persons pass through. The conductors are not guarded. Which installation satisfies 690.31(A)(2)?
- A Open conductors supported on insulators
- B Any listed single-conductor cable, jacketed or not
- C Type MC cable
- D Type MC cable is only required if the voltage exceeds 100 volts
Show answer & explanation
Correct: C — Type MC cable
Per 690.31(A)(2), PV dc circuit conductors over 30 volts that are readily accessible to unqualified persons and not guarded must be installed in Type MC cable, multiconductor jacketed cable, or raceway. Unjacketed single-conductor cable and open conductors don't meet this, and the 30-volt threshold — not 100 volts — is what triggers the requirement.
Rapid Shutdown Labeling Requirements
NEC 690.12(D) Every rapid shutdown-equipped PV building needs a permanent label at service equipment with exact wording, plus a switch label within 3 ft in white-on-red.
Q28 NEC 690.12(D) Code lookup
A rooftop PV installation has a single rapid shutdown type for the entire array, and the permanent label required at the service equipment must show a diagram of the building roof plus specific wording about the rapid shutdown switch. Which section specifies the exact wording and lettering requirements for this label at the service equipment?
- A 690.12(D)
- B 690.12(D)(1)
- C 690.12(D)(2)
- D 690.13(B)
Show answer & explanation
Correct: A — 690.12(D)
690.12(D) sets the label content, roof diagram, and 3/8 in. capitalized lettering for the label at the service equipment location. 690.12(D)(1) only adds a detailed roof plan view for buildings with more than one rapid shutdown type or none, and 690.13(B) covers disconnect marking, not rapid shutdown labeling.
Calculating Max Voltage for DC-to-DC Converter Circuits
NEC 690.7(B) Use the converter's listing instructions to find max voltage; if none is given, use the rated output voltage for a single converter or the sum of rated outputs for series-connected converters.
Q29 NEC 690.7(B)
A PV circuit is connected to the output of a single dc-to-dc converter. The converter's listing and labeling instructions do not include a method for calculating maximum voltage. Per 690.7(B)(1), what is the maximum voltage?
- A The open-circuit voltage of the PV source circuit adjusted for temperature
- B The nameplate voltage of the utility-interactive inverter
- C The sum of the rated voltage outputs of all converters in the array
- D The maximum rated voltage output of the dc-to-dc converter
Show answer & explanation
Correct: D — The maximum rated voltage output of the dc-to-dc converter
Under 690.7(B)(1), when the listing instructions don't specify a method, the maximum voltage defaults to the converter's maximum rated voltage output. Summing outputs applies only to series-connected converters under 690.7(B)(2), not a single unit. Temperature-adjusted open-circuit voltage is a PV source circuit calculation under a different part of 690.7, not the dc-to-dc converter output calculation.