Free NEC practice test · Article 426

Deicing and Snow-Melting Equipment practice questions

A free NEC Article 426 practice test for the journeyman exam: 13 questions on Fixed Outdoor Electric Deicing and Snow-Melting Equipment, each with the answer and the why behind it.

13 questions · free · answers included NEC 2023 · Updated

How to use this practice test

These 13 journeyman-exam practice questions cover NEC Article 426 across 13 code concepts, every one with the correct answer and a plain-English explanation of the rule behind it. They come from the same question bank the Loomi app trains you on — this is the free web sample, not a separate watered-down set.

Work straight down the sheet and answer before you peek: each question hides its answer behind Show answer & explanation. Questions tagged Code lookup are speed drills — race your codebook to the cited section. Printing this page gives you a clean paper worksheet with the answers left off.

Embedded heating system installation — cover depth, securing, expansion joints

NEC 426.20(C)

Embedded heating units need at least 38 mm of cover, must be held in place while the finish is poured, and can't cross expansion joints unless the design allows for movement.

Q1 NEC 426.20(C)

An embedded heating cable is installed on a substantial concrete base 50 mm (2 in.) thick. What is the minimum required cover of concrete applied over the cable?

  1. A 50 mm (2 in.)
  2. B 38 mm (1½ in.)
  3. C 90 mm (3½ in.)
  4. D 25 mm (1 in.)
Show answer & explanation

Correct: B — 38 mm (1½ in.)

426.20(C)(1) requires at least 38 mm (1½ in.) of concrete, masonry, or asphalt over the units, panels, or cables when the base itself is at least 50 mm thick. The 90 mm figure is the maximum embedment depth allowed for the alternate 'other identified base' option in 426.20(C)(2), not the minimum cover here, and 25 mm doesn't meet the code minimum.

Disconnecting means for fixed and cord-and-plug deicing equipment

NEC 426.50

Fixed deicing equipment needs a lockable, indicating disconnect for all ungrounded conductors; small cord-and-plug units can use the plug itself.

Q2 NEC 426.50 Code lookup

A homeowner has a fixed outdoor snow-melting mat installed in a concrete driveway, wired directly to a dedicated branch circuit (not cord-and-plug). The branch-circuit breaker is readily accessible to the homeowner. Which section allows that breaker to serve as the required disconnecting means for the deicing equipment, provided it is of the indicating type and lockable in the open position?

  1. A 426.51(A)
  2. B 426.50(B)
  3. C 426.50(A)
  4. D 426.28
Show answer & explanation

Correct: C — 426.50(A)

426.50(A) governs fixed outdoor deicing equipment and expressly permits the branch-circuit switch or breaker to serve as the simultaneous-disconnection means when readily accessible, indicating, and lockable in the open position. 426.51(A) instead covers temperature controllers with an off position, which is a control function, not the disconnecting means.

Temperature controllers: when they can serve as the disconnecting means

NEC 426.51

A temperature controller can only double as the disconnecting means if it has an "off" position, opens all ungrounded conductors, and can be locked open per 110.25.

Q3 NEC 426.51

A de-icing system's temperature controller has an "off" position and opens all ungrounded conductors when switched off. Under what additional condition can it serve as the disconnecting means?

  1. A It must be located within sight of the heating equipment
  2. B It must be rated for at least 125% of the connected load
  3. C It must be capable of being locked in the open position per 110.25
  4. D It must be a remote controlled device
Show answer & explanation

Correct: C — It must be capable of being locked in the open position per 110.25

426.51(A) requires that a temperature controller with an "off" position be capable of being locked in the open position per 110.25 before it can serve as the disconnecting means. Load rating and sight-line rules aren't the qualifying condition in this section, and 426.51(C) actually bars remote controlled devices from serving as the disconnect at all.

Exposed heating element mounting requirements

NEC 426.21(A)

Exposed deicing and snow-melting heating elements must be secured by identified means, kept within temperature limits, and installed to handle expansion, contraction, and structure flex.

Q4 NEC 426.21(A)

An exposed snow-melting heating element assembly is mounted on a roof edge with no direct contact with the surface being heated. What does 426.21(B) require of the design?

  1. A The assembly must be rated for wet locations regardless of exposure
  2. B The assembly must be secured with identified fasteners at 12 in. intervals
  3. C The assembly's design must ensure its temperature limitations are not exceeded
  4. D The assembly must include a ground-fault protection device
Show answer & explanation

Correct: C — The assembly's design must ensure its temperature limitations are not exceeded

Per 426.21(B), when the heating element is not in direct contact with the surface being heated, the heater assembly's design must keep it from exceeding its temperature limitations. Securing method is a separate requirement under 426.21(A), and GFCI or wet-location rating are not what this subsection addresses.

Nonheating leads for exposed deicing equipment

NEC 426.23(A)

Cold leads on exposed deicing/snow-melting heaters must be rated for the temperature they'll see, keep 6 in. of lead inside the junction box, and run in rigid metal conduit, IMC, EMT, or another approved raceway.

Q5 NEC 426.23(A)

An electrician is installing exposed deicing/snow-melting equipment. What is the minimum length of nonheating lead that must be provided within the junction box?

  1. A 300 mm (12 in.)
  2. B 75 mm (3 in.)
  3. C 150 mm (6 in.), but only if the leads are field-assembled
  4. D 150 mm (6 in.)
Show answer & explanation

Correct: D — 150 mm (6 in.)

426.23(A) requires not less than 150 mm (6 in.) of nonheating leads within the junction box, regardless of whether the leads are factory preassembled or field-assembled. The 75 mm and 300 mm options are fabricated distances, and the length requirement isn't conditioned on assembly type.

Grounding braid or sheath for heated sections

NEC 426.27

The grounding means for a deicing or snow-melting cable, panel, or unit — copper braid, metal sheath, or other approved means — must be built into the heated section itself, not supplied separately.

Q6 NEC 426.27 Code lookup

A crew is installing a self-regulating heating cable for a roof deicing system. The heated section of the cable must include copper braid, metal sheath, or another approved means for what purpose — which section specifies this requirement?

  1. A 426.27
  2. B 426.24
  3. C 426.28
  4. D 426.26
Show answer & explanation

Correct: A — 426.27

426.27 requires grounding means (copper braid, metal sheath, or other approved means) as part of the heated section itself. 426.28 covers ground-fault protection of the circuit (a different safeguard), and 426.26 covers corrosion protection, not grounding of the heated section.

Corrosion protection for deicing system enclosures

NEC 426.26

Metal raceways, boxes, and fittings for fixed outdoor deicing and snow-melting equipment must resist corrosion when buried, embedded in concrete, or exposed to severe corrosive conditions.

Q7 NEC 426.26 Code lookup

A snow-melting cable installation runs metal raceway and boxes embedded directly in a concrete driveway slab that is also exposed to deicing salts. Which section governs the material or corrosion-protection requirements for these enclosures and raceways in this condition?

  1. A 426.26
  2. B 426.25
  3. C 426.27
  4. D 426.28
Show answer & explanation

Correct: A — 426.26

426.26 specifically requires ferrous and nonferrous raceways, boxes, fittings, and supports installed in concrete, in direct earth contact, or in severely corrosive areas to be of suitable material or provided with identified corrosion protection. 426.27 instead addresses grounding braid or sheath continuity, and 426.25 covers equipment marking, so neither answers a materials/corrosion question.

General installation requirements for deicing/snow-melting equipment

NEC 426.10

Outdoor deicing and snow-melting equipment must be listed for the outdoor environment, installed per the manufacturer's instructions, and protected from physical damage.

Q8 NEC 426.10 Code lookup

A contractor is installing an electric snow-melting mat under a concrete driveway apron. Before installation, which section requires the equipment to be identified as suitable for the outdoor environment and installed per the manufacturer's instructions?

  1. A 426.12
  2. B 426.13
  3. C 426.10
  4. D 426.11
Show answer & explanation

Correct: C — 426.10

426.10 is the general requirement that deicing/snow-melting equipment be identified as suitable for the environment and installed per manufacturer instructions. 426.11 only addresses protecting exposed heating equipment from physical damage, not the identification/manufacturer-instructions requirement.

What counts as fixed deicing/snow-melting equipment

NEC 426.1

Article 426 covers fixed outdoor deicing and snow-melting equipment only — embedded in surfaces like driveways or exposed on roofs and drainage systems.

Q9 NEC 426.1

Under Article 426, a heating cable embedded in a concrete driveway to melt snow is classified as which type of application?

  1. A Embedded
  2. B Exposed
  3. C Portable
  4. D Interior
Show answer & explanation

Correct: A — Embedded

Section 426.1(A) lists driveways, walks, and steps as embedded applications — the heating equipment is buried within the surface. Exposed applications, by contrast, are mounted on structures like roofs or bridges per 426.1(B); Article 426 doesn't use "portable" or "interior" as classification terms.

Thermal guarding for high-temperature deicing equipment surfaces

NEC 426.12

Any outdoor deicing or snow-melting equipment surface running hotter than 60°C (140°F) must be guarded, isolated, or insulated so people can't accidentally touch it.

Q10 NEC 426.12

An outdoor snow-melting mat's exposed surface reaches 82°C (180°F) during operation in an area where people walk. Per 426.12, what is required?

  1. A A GFCI must be installed ahead of the equipment
  2. B The surface must be guarded, isolated, or thermally insulated to prevent contact
  3. C The circuit must be derated by 20% for the surface temperature
  4. D Nothing, since the equipment is listed for outdoor use
Show answer & explanation

Correct: B — The surface must be guarded, isolated, or thermally insulated to prevent contact

426.12 requires that outdoor deicing/snow-melting equipment surfaces exceeding 60°C (140°F) be physically guarded, isolated, or thermally insulated against contact by people in the area. GFCI protection and circuit derating address shock and overcurrent concerns, not thermal contact hazards, and being listed for outdoor use doesn't exempt equipment from this contact-protection requirement.

Embedded heating system sizing — watt density and cable spacing

NEC 426.20(A)

Embedded deicing panels are capped at 1300 watts/m2 (120 watts/ft2), and cable runs must be spaced at least 25 mm (1 in.) on centers.

Q11 NEC 426.20(A)

A designer is laying out an embedded snow-melting panel for a driveway. Per 426.20(A), what is the maximum permitted watt density?

  1. A 1300 watts/m2 (120 watts/ft2) of heated area
  2. B 1000 watts/m2 (100 watts/ft2) of heated area
  3. C 1300 watts/m2 (120 watts/ft2) of the total slab area, heated or not
  4. D 1500 watts/m2 (140 watts/ft2) of heated area
Show answer & explanation

Correct: A — 1300 watts/m2 (120 watts/ft2) of heated area

426.20(A) caps panels or units at 1300 watts/m2 (120 watts/ft2) of heated area specifically, not total slab area. The 1500/140 and 1000/100 figures are plausible but incorrect round-number substitutions.

Embedded nonheating leads — grounding, splices, and raceway entry

NEC 426.22(A)

Nonheating leads buried in concrete, masonry, or asphalt need a grounding sheath/braid or metal raceway, and the buried splice to the heating element must sit 1–6 in. from that raceway.

Q12 NEC 426.22(A)

Per 426.22(B), where must the splice connection between the nonheating lead and the heating element be located relative to the metal raceway, when embedded in concrete, masonry, or asphalt?

  1. A Anywhere within the embedded run, as long as it is accessible for inspection
  2. B At least 150 mm (6 in.) from the raceway, with no maximum specified
  3. C No less than 25 mm (1 in.) and no more than 150 mm (6 in.) from the raceway
  4. D Immediately at the raceway opening, with no minimum separation required
Show answer & explanation

Correct: C — No less than 25 mm (1 in.) and no more than 150 mm (6 in.) from the raceway

426.22(B) sets both a floor and a ceiling: the splice must be no less than 25 mm (1 in.) and no more than 150 mm (6 in.) from the metal raceway. A splice right at the raceway opening, one placed farther than 6 in. away, or one located anywhere convenient in the embedded run would all violate this specific placement window.

Embedded nonheating leads — expansion joints, grade transition, junction box length

NEC 426.22(D)

Cold leads need protection where the slab moves, where they leave the ground, and 6 in. of slack wherever they land in a junction box.

Q13 NEC 426.22(D)

How much free nonheating lead must be present within a junction box per 426.22(F)?

  1. A No minimum is specified, only that splices be accessible
  2. B 150 mm (6 in.)
  3. C 300 mm (12 in.)
  4. D 75 mm (3 in.)
Show answer & explanation

Correct: B — 150 mm (6 in.)

426.22(F) sets the minimum at 150 mm (6 in.) of free nonheating lead within the junction box. 300 mm and 75 mm are plausible-sounding but incorrect lengths, and the rule does specify an explicit minimum rather than leaving it unstated.

Loomi · NEC exam prep

2,035 questions free on the web. 12,934 in the app.

Loomi's full journeyman bank is timed, NEC-referenced, and runs on spaced repetition that hammers what you miss. Try everything free for 3 days.

Get launch access