Ground-fault protection of equipment: when required and how it is set
NEC 230.95 GFPE kicks in on solidly grounded wye services over 150V to ground (up to 1000V phase-to-phase) with a 1000A+ disconnect, tripping at no more than 1200A within 1 second at 3000A or more.
Q1 NEC 230.95
A solidly grounded wye service operates at 277/480V with a service disconnect rated 1200 amperes. Under 230.95, what is required?
- A No ground-fault protection, since 480V exceeds the covered range
- B Ground-fault protection of equipment
- C Ground-fault protection only if the disconnect uses fuses rather than a circuit breaker
- D Ground-fault protection only if the load is a continuous industrial process
Show answer & explanation
Correct: B — Ground-fault protection of equipment
230.95 requires GFPE for solidly grounded wye services over 150V to ground but not exceeding 1000V phase-to-phase, for disconnects rated 1000A or more. A 277/480V system falls within that range (277V to ground, 480V phase-to-phase), and 1200A meets the threshold, so protection is required. The industrial-process exception only removes the requirement for nonorderly shutdown hazards, and fuses vs. breakers doesn't change applicability.
Service disconnect: purpose and location rules
NEC 230.70 The service disconnect must be readily accessible, placed outside or nearest the point of entrance inside, never in a bathroom, and permanently marked.
Q2 NEC 230.70
An electrician wants to place the service disconnecting means inside a dwelling. Where does the NEC require it to be located?
- A Anywhere inside the building as long as it is readily accessible
- B At a readily accessible location nearest the point of entrance of the service conductors
- C In a mechanical room regardless of distance from the service entrance
- D In the bathroom nearest the electrical panel
Show answer & explanation
Correct: B — At a readily accessible location nearest the point of entrance of the service conductors
230.70(A)(1) requires the service disconnect to be readily accessible either outside the building or, if inside, nearest the point of entrance of the service conductors — not just anywhere readily accessible inside. Bathrooms are explicitly prohibited under 230.70(A)(2).
Service overcurrent protection: rating and placement rules
NEC 230.90 Every ungrounded service conductor needs overload protection sized no higher than its ampacity, and the grounded conductor can never hold a fuse or single-pole breaker.
Q3 NEC 230.90
Under 230.90(A), the rating or setting of the overcurrent device protecting an ungrounded service conductor must be:
- A Not higher than 80% of the conductor ampacity
- B Equal to the service disconnect rating regardless of conductor size
- C Not higher than the ampacity of the conductor
- D At least 125% of the conductor ampacity
Show answer & explanation
Correct: C — Not higher than the ampacity of the conductor
230.90(A) requires the overcurrent device's rating or setting to be not higher than the ampacity of the ungrounded service conductor it protects. The 125%-of-ampacity option and the 80%-of-ampacity option both invert or misapply continuous-load sizing concepts from other parts of the Code, and tying the rating strictly to the disconnect rating ignores the conductor ampacity limit this section actually sets.
What equipment may connect ahead of the service disconnect
NEC 230.82 Only a specific list in 230.82 may connect on the supply side of the service disconnect — everything else must wait until after it.
Q4 NEC 230.82
Which of the following is explicitly permitted to connect to the supply side of the service disconnecting means under 230.82?
- A Cable limiters
- B A general-purpose fused disconnect switch for a subpanel
- C A branch-circuit panelboard for lighting loads
- D A standard GFCI receptacle circuit
Show answer & explanation
Correct: A — Cable limiters
230.82(1) permits cable limiters on the supply side. General panelboards, branch circuits, and receptacle circuits are downstream loads that must be fed from the load side of the service disconnect, not the supply side.
When additional services are permitted
NEC 230.2 A building normally gets one service, but 230.2 lists specific exceptions — special conditions, special occupancies, capacity over 2000A, or different electrical characteristics.
Q5 NEC 230.2
Under which condition can an additional service be installed solely because of load capacity?
- A Capacity requirements exceed 2000 amperes at 1000 volts or less
- B The building requires two different voltages
- C The building has more than one tenant
- D The load exceeds 400 amperes at 240 volts
Show answer & explanation
Correct: A — Capacity requirements exceed 2000 amperes at 1000 volts or less
230.2(C) permits an additional service where capacity requirements exceed 2000 amperes at a supply voltage of 1000 volts or less. Multiple tenants alone falls under the special-occupancy provision in 230.2(B), a lower amperage doesn't trigger this exception, and different voltages are addressed separately under 230.2(D).
Overhead conductor clearance above roofs
NEC 230.24(A) Overhead service conductors need 8 ft 6 in. of vertical clearance above a roof, extended 3 ft past every edge, unless a specific exception in 230.24(A) applies.
Q6 NEC 230.24(A)
An electrician is routing overhead service conductors over a flat, low-slope roof with no special conditions. What is the minimum required vertical clearance above the roof surface?
- A 3.7 m (12 ft)
- B 450 mm (18 in.)
- C 2.6 m (8 ft 6 in.)
- D 900 mm (3 ft)
Show answer & explanation
Correct: C — 2.6 m (8 ft 6 in.)
230.24(A) sets the base vertical clearance above a roof at 2.6 m (8 ft 6 in.), maintained 900 mm (3 ft) from the roof edge in all directions. The 900 mm (3 ft) and 450 mm (18 in.) figures are reduced clearances that only apply under specific exceptions (steep slope, guarded roof, or short overhang), none of which apply here.
Vertical clearance from final grade by area type
NEC 230.24(B) Overhead service conductor height above grade scales with what's underneath and the voltage — from 10 ft over a pedestrian walk up to 24 ft over railroad tracks.
Q7 NEC 230.24(B)
Overhead service conductors cross a residential driveway at 240 volts to ground. What is the minimum vertical clearance from final grade?
- A 4.5 m (15 ft)
- B 3.0 m (10 ft)
- C 3.7 m (12 ft)
- D 5.5 m (18 ft)
Show answer & explanation
Correct: C — 3.7 m (12 ft)
Per 230.24(B)(2), residential property and driveways at or under 300 volts to ground require 3.7 m (12 ft). The 15 ft option applies only once voltage exceeds 300 volts, the 18 ft option is for streets and truck traffic, and 10 ft only applies to pedestrian-only areas under the messenger-supported, 150-volt condition.
Minimum disconnect ratings by installation type
NEC 230.79 Every service disconnect must be rated for the calculated load, but it can never go below the floor set for its installation type — 100 A for a one-family dwelling.
Q8 NEC 230.79
What is the minimum allowable rating for a service disconnecting means installed at a one-family dwelling?
- A 15 amperes
- B 60 amperes
- C 30 amperes
- D 100 amperes, 3-wire
Show answer & explanation
Correct: D — 100 amperes, 3-wire
230.79(C) sets a 100-ampere, 3-wire minimum specifically for one-family dwellings. The 60 A minimum applies to 'all other' installations under 230.79(D), 30 A applies to two 2-wire branch circuits under 230.79(B), and 15 A applies only to single branch circuit installations under 230.79(A) — none of those apply once the installation is a one-family dwelling.
Emergency disconnect for one- and two-family dwellings
NEC 230.85 Every one- and two-family dwelling needs an outdoor, readily accessible emergency disconnect rated for available fault current, and if there's more than one, they must be grouped.
Q9 NEC 230.85
For a one-family dwelling, where is the emergency disconnecting means required to be installed?
- A In any accessible location, indoor or outdoor, within the dwelling's electrical room
- B Anywhere on the property, regardless of visibility from the dwelling
- C In a readily accessible outdoor location on or within sight of the dwelling unit
- D Inside the dwelling within 6 ft of the panelboard
Show answer & explanation
Correct: C — In a readily accessible outdoor location on or within sight of the dwelling unit
230.85(A)(1) requires the emergency disconnect to be in a readily accessible outdoor location on or within sight of the dwelling unit, unless 225.41 is met. An indoor location or an unrestricted anywhere-on-property placement does not satisfy the sight/accessibility requirement.
Emergency disconnect marking and other-source plaque
NEC 230.85(E) First responders need to read one glance and know exactly what a disconnect does — the exact wording, red background, white text, and 1/2-in. letters are all required, and any other energy source not next to it needs its own directory plaque.
Q10 NEC 230.85(E)
A dwelling has a solar PV system with its own disconnect located on the opposite side of the house from the required emergency disconnect. What does 230.85(D) require?
- A No action is required since the PV disconnect is a separate energy source
- B The PV disconnect must be relocated next to the emergency disconnect
- C A plaque or directory adjacent to the emergency disconnect identifying the location of the PV disconnect
- D The PV disconnect must be marked EMERGENCY DISCONNECT, NOT SERVICE EQUIPMENT
Show answer & explanation
Correct: C — A plaque or directory adjacent to the emergency disconnect identifying the location of the PV disconnect
230.85(D) requires a plaque or directory adjacent to the emergency disconnect when other energy source isolation equipment (like a PV disconnect per 705.20) isn't located next to it — relocating the equipment isn't required, and the special EMERGENCY DISCONNECT wording in 230.85(E)(1) applies only to service-related disconnects, not other energy sources.
Grouping multiple disconnects and occupant access
NEC 230.72 When a service has two to six disconnects they must be grouped and marked, but a fire-pump water supply disconnect and any emergency/standby disconnects are the exceptions that get installed apart on purpose.
Q11 NEC 230.72
A building has five service disconnects permitted under 230.71. What does 230.72(A) require regarding their installation?
- A They must be grouped, and each marked to indicate the load served
- B They must be spaced at least 6 ft apart to allow individual servicing
- C Only the largest disconnect needs to be marked with its load
- D They must each be installed in a separate room for isolation
Show answer & explanation
Correct: A — They must be grouped, and each marked to indicate the load served
230.72(A) requires that the two to six permitted disconnects be grouped and that each one be marked to indicate the load it serves. There's no separate-room or spacing requirement, and every disconnect — not just the largest — must be marked.
Up to six service disconnects: when and how
NEC 230.71 A service normally gets one disconnect, but 230.71(B) allows up to six if they're split across specific enclosure types like separate cabinets, panelboards, or switchgear compartments.
Q12 NEC 230.71
Under 230.71(B), which arrangement is permitted for providing four service disconnecting means for one service?
- A Four disconnects in a single switchboard vertical section
- B Four separate enclosures, each with its own main service disconnecting means
- C Four circuit breakers grouped together in a single panelboard enclosure with one main disconnect
- D Four disconnects in one motor control center unit with no barriers
Show answer & explanation
Correct: B — Four separate enclosures, each with its own main service disconnecting means
230.71(B)(1) permits separate enclosures, each with its own main service disconnecting means, as one of the allowed combinations. A single panelboard enclosure with only one main disconnect doesn't provide four separate disconnecting means as required, and motor control centers are capped at two service disconnects per unit with barriers required — not four with none. A single switchboard vertical section is limited to one service disconnect per section under 230.71(B)(3).
Sizing and ampacity of overhead service conductors
NEC 230.23 Overhead service conductors must be sized for the calculated load per Article 220, but can never go smaller than 8 AWG copper or 6 AWG aluminum regardless of how light the load is.
Q13 NEC 230.23
A dwelling's overhead service conductors are being sized. Per 230.23(B), what is the smallest copper conductor permitted for a general overhead service?
- A 10 AWG copper
- B 8 AWG copper
- C 12 AWG copper
- D 6 AWG copper
Show answer & explanation
Correct: B — 8 AWG copper
230.23(B) sets the general minimum at 8 AWG copper (or 6 AWG aluminum/copper-clad aluminum). The 12 AWG copper option is only allowed under the narrow exception for a single limited-load branch circuit, and 6 AWG and 10 AWG copper are not the stated general minimum.
Overhead service locations: service heads, goosenecks, and placement
NEC 230.54 The service head or gooseneck must sit above the service-drop attachment point, and if that's not practical, no farther than 24 in. from it.
Q14 NEC 230.54
An electrician finds it impracticable to mount the service head above the point of attachment of the service-drop conductors. Per 230.54(C), what is the maximum allowed distance from the point of attachment?
- A There is no allowance — it must always be above the attachment point
- B 900 mm (36 in.)
- C 300 mm (12 in.)
- D 600 mm (24 in.)
Show answer & explanation
Correct: D — 600 mm (24 in.)
230.54(C) permits the service head or gooseneck to be located not farther than 600 mm (24 in.) from the point of attachment when placing it above is impracticable. The 300 mm and 900 mm figures are not the code-specified distance, and an allowance does exist for this exact scenario.
Sizing service-entrance conductors for ampacity and load
NEC 230.42 Size SE conductors to the larger of the 125%-continuous-load calculation or the corrected/adjusted ampacity for the actual load — never less than either.
Q15 NEC 230.42
A service supplies a mix of continuous and noncontinuous loads. Per 230.42(A)(1), how must the ungrounded service-entrance conductors be sized, assuming no 100%-rated assembly applies?
- A Ampacity not less than 80% of the total combined load
- B Ampacity not less than 125% of the total combined load
- C Ampacity not less than 125% of the continuous load plus 100% of the noncontinuous load
- D Ampacity not less than 100% of the continuous load plus 100% of the noncontinuous load
Show answer & explanation
Correct: C — Ampacity not less than 125% of the continuous load plus 100% of the noncontinuous load
230.42(A)(1) requires an ampacity not less than the sum of the noncontinuous loads plus 125 percent of continuous loads. Applying 125% to the entire combined load, or applying no multiplier at all, misstates the rule — the 125% factor applies only to the continuous portion.
Approved wiring methods for service-entrance conductors (≤1000V)
NEC 230.43 Service-entrance conductors must use one of the specific wiring methods listed in 230.43 — you can't just pick any raceway or cable.
Q16 NEC 230.43
An electrician wants to run 10 ft of liquidtight flexible metal conduit (LFMC) between the service raceway and the service equipment. Is this permitted under 230.43?
- A Yes, but only if EMT is used for the remainder of the run
- B Yes, LFMC has no length restriction as a service-entrance wiring method
- C No, LFMC is limited to 1.8 m (6 ft) when used this way, and requires a supply-side bonding jumper
- D No, LFMC is never permitted for service-entrance conductors
Show answer & explanation
Correct: C — No, LFMC is limited to 1.8 m (6 ft) when used this way, and requires a supply-side bonding jumper
230.43(15) permits LFMC as a service-entrance wiring method only when not over 1.8 m (6 ft) long between a raceway, or between a raceway and service equipment, and only with a supply-side bonding jumper routed with it per 250.102(A), (B), (C), and (E). A 10 ft run exceeds that limit, ruling out the no-restriction option. LFMC is listed in 230.43, so it isn't categorically excluded, and the length limit applies regardless of what other raceway type is used elsewhere.
Occupancies requiring a surge-protective device
NEC 230.67(A) Services feeding dwelling units, dormitories, hotel/motel guest rooms, and nursing home patient sleeping rooms must have an SPD — no exceptions listed for these four.
Q17 NEC 230.67(A)
Under 230.67(A), a surge-protective device is required on the service for which of the following?
- A A standalone industrial machine shop
- B A commercial warehouse with no sleeping areas
- C An open-air parking structure
- D A guest suite in a motel
Show answer & explanation
Correct: D — A guest suite in a motel
230.67(A)(3) lists guest rooms and guest suites of hotels and motels as a mandatory SPD occupancy. The warehouse, parking structure, and machine shop are not among the four listed occupancy types in 230.67(A).
Underground service conductor insulation and allowed wiring methods
NEC 230.30 Underground service conductors must be insulated for the voltage applied, except for specific bare-copper and cable-assembly exceptions, and only certain wiring methods are allowed.
Q18 NEC 230.30
Under which condition may a bare copper grounded conductor be used for a direct-buried underground service, regardless of soil conditions?
- A When it is part of a cable assembly identified for underground use
- B When it is installed in a raceway
- C When the local soil is classified as low-corrosivity
- D When the conductor is sized one size larger than required
Show answer & explanation
Correct: A — When it is part of a cable assembly identified for underground use
Per 230.30(A)(3), bare copper used for direct burial is permitted without regard to soil conditions when it's part of a cable assembly identified for underground use. Bare copper direct-buried outside a cable assembly still requires soil conditions that approve bare copper (230.30(A)(2)), and bare copper in a raceway is a separate allowance under 230.30(A)(1) that doesn't address direct burial.
When service conductors count as 'outside' the building
NEC 230.6 Service conductors can physically pass through or under a building and still be legally 'outside' it if they meet one of five specific installation conditions in 230.6.
Q19 NEC 230.6 Code lookup
A service raceway runs beneath a warehouse floor and is encased in concrete only 25 mm (1 in.) thick, not the full 50 mm (2 in.) required. The contractor wants to confirm whether these conductors still qualify as being outside the building for clearance purposes. Which section lists the exact conditions under which service conductors are considered outside a building?
- A 230.9
- B 230.8
- C 230.6
- D 230.24
Show answer & explanation
Correct: C — 230.6
230.6 lists the specific installation methods (concrete encasement thickness, burial depth, vault construction, etc.) that let conductors run through a building yet still be treated as outside it. 230.9 and 230.24 address clearances for conductors already established as outside, and 230.8 covers raceway seals — neither defines what counts as 'outside.'
Ground-fault protection: required on-site performance testing
NEC 230.95(C) Ground-fault protection systems must be field-tested with primary current injection by a qualified person, and the test record must be kept for the AHJ.
Q20 NEC 230.95(C)
When a ground-fault protection system is first installed on site, what does 230.95(C) require?
- A A secondary injection test performed annually thereafter
- B A visual inspection by the installing electrician only
- C A manufacturer sign-off letter in lieu of on-site testing
- D A performance test using primary current injection, conducted by a qualified person
Show answer & explanation
Correct: D — A performance test using primary current injection, conducted by a qualified person
230.95(C) requires the ground-fault protection system be performance tested on site when first installed, using primary current injection performed by a qualified person, per the equipment instructions. A visual inspection alone or a manufacturer letter does not satisfy this; the section doesn't establish an annual secondary-injection retest requirement.
Marking/directory required when a building has multiple services
NEC 230.2(E) Any building fed by more than one service, or by a mix of services and feeders/branch circuits, needs a permanent plaque or directory at every service disconnect location.
Q21 NEC 230.2(E)
A building is supplied by two separate services. Per 230.2(E), what is required at the service disconnect locations?
- A A permanent plaque or directory at each service disconnect location identifying all other services, feeders, and branch circuits and the area each serves
- B No marking is required as long as both services are properly grounded and bonded
- C A written justification filed with the authority having jurisdiction explaining why two services were needed
- D A single plaque at the main service disconnect only, since the other disconnect is considered secondary
Show answer & explanation
Correct: A — A permanent plaque or directory at each service disconnect location identifying all other services, feeders, and branch circuits and the area each serves
230.2(E) requires a permanent plaque or directory at EACH service disconnect location, not just one, denoting all other services, feeders, and branch circuits supplying the building and the area served by each. There's no AHJ justification filing requirement in this section, and grounding/bonding compliance doesn't substitute for the identification requirement.
One set of service-entrance conductors per service drop/lateral
NEC 230.40 Each service drop, overhead run, underground run, or lateral feeds only one set of service-entrance conductors, with narrow exceptions for multi-occupancy buildings, dwellings, and grouped disconnects.
Q22 NEC 230.40
A multiple occupancy building has 9 service disconnect locations for a single supply classification. Per 230.40, what does the code require?
- A Plaques identifying all service disconnect locations and supply sources, posted at approved readily accessible locations near each point of attachment or entry
- B Reducing the number of disconnect locations to six or fewer before service can be installed
- C A single set of service-entrance conductors run to all 9 locations
- D Applying the 230.2(E) requirements only at the primary disconnect location
Show answer & explanation
Correct: A — Plaques identifying all service disconnect locations and supply sources, posted at approved readily accessible locations near each point of attachment or entry
230.40 states that once the number of service disconnect locations for a given supply classification exceeds six, plaques describing all disconnect locations and sources must be posted at approved, readily accessible locations near each service drop or lateral attachment/entry point. The six-or-fewer threshold only triggers the simpler 230.2(E) requirement at each location; it doesn't cap or force a redesign of disconnect count.
Using cable trays to support service-entrance conductors
NEC 230.44 Cable trays can support service-entrance conductors, but the tray must be limited to approved cable/conductor types, labeled every 10 ft, and other conductors need a solid barrier to separate them.
Q23 NEC 230.44
A contractor wants to run single conductors (not in a cable assembly) as service-entrance conductors in a cable tray. What size restriction applies?
- A Any size is permitted as long as it is copper
- B They must be 2/0 AWG or larger and listed for use in cable tray
- C They must be 4 AWG or larger and listed for use in cable tray
- D They must be 1/0 AWG or larger and listed for use in cable tray
Show answer & explanation
Correct: D — They must be 1/0 AWG or larger and listed for use in cable tray
230.44(5) permits single conductors 1/0 and larger that are listed for use in cable tray. The 4 AWG and 2/0 AWG thresholds are plausible-sounding but incorrect minimums, and unrestricted sizing ignores the listing and size requirement entirely.
Protecting service-entrance conductors from physical damage
NEC 230.50 Underground SE conductors follow 300.5 burial protection; above-grade SE cables need rigid raceway or equivalent, and open conductors can't run within 10 ft of grade where exposed.
Q24 NEC 230.50 Code lookup
A residential service using individual open conductors runs down the exterior wall to the meter base. Which section limits how close those open conductors can be to grade level before they need protection or must be run some other way?
- A 230.50(B)(2)
- B 230.54(D)
- C 230.50(B)(1)
- D 230.51(C)
Show answer & explanation
Correct: A — 230.50(B)(2)
230.50(B)(2) sets the 3.0 m (10 ft) grade-level clearance for individual open conductors and cables (other than SE cable). 230.50(B)(1) instead lists the raceway/conduit types approved to shield SE cable from physical damage, and 230.51(C) covers securing/support spacing for open conductors, not clearance from grade.
Using a service mast to support overhead conductors
NEC 230.28 A service mast can only carry service conductors, must be strong enough (or braced) for the pull, and conductors can't attach between the weatherhead and a coupling above the roofline.
Q25 NEC 230.28 Code lookup
A homeowner wants the service-drop conductors attached directly to a rigid conduit service mast that also serves as the raceway for the service-entrance conductors. Which section covers the structural and fitting requirements the mast itself must meet to safely carry that pulling strain?
- A 230.24(B)
- B 230.29
- C 230.28(A)
- D 230.28(B)
Show answer & explanation
Correct: C — 230.28(A)
230.28(A) sets the strength requirement for a service mast (adequate strength or braces/guy wires) and requires identified hubs for conduit used as a mast. 230.28(B) instead governs where conductors may be attached relative to the weatherhead and coupling, not the mast's structural adequacy.
Simultaneous pole opening and grounded conductor disconnection
NEC 230.74 The service disconnect must open all ungrounded conductors at once, and the grounded conductor needs its own dedicated disconnecting means if the main disconnect doesn't already break it.
Q26 NEC 230.74 Code lookup
A single-family dwelling has a 200A service with one main breaker in the meter/main combo panel. The breaker is a single-throw handle that opens both hot legs at once when tripped or switched off. Which section requires that a service disconnect open all ungrounded conductors it controls simultaneously?
- A 230.72
- B 230.75
- C 230.71
- D 230.74
Show answer & explanation
Correct: D — 230.74
230.74 requires each service disconnect to simultaneously disconnect all ungrounded conductors it controls. 230.75 covers disconnecting the grounded (neutral) conductor, a different function, and 230.71 only addresses the maximum number of disconnects allowed, not simultaneous operation.
SPD placement, type, and discharge rating
NEC 230.67(B) The required surge arrester must sit at or right after the service equipment (or a downstream distribution point), be Type 1 or Type 2, and rated at least 10kA.
Q27 NEC 230.67(B)
An electrician wants to install the required SPD at a distribution panel instead of at the service equipment. Under what condition is this permitted?
- A Only if the distribution panel is the next level of distribution equipment downstream toward the load
- B Never — the SPD must always be integral to or immediately adjacent to the service equipment
- C Only if the discharge current rating is increased to at least 20kA
- D Only if the SPD is rated Type 3
Show answer & explanation
Correct: A — Only if the distribution panel is the next level of distribution equipment downstream toward the load
230.67(B) allows the SPD location requirement to be satisfied at the next level of distribution equipment downstream toward the load, instead of at the service equipment. There's no Type 3 option under 230.67(C) and no 20kA alternate threshold under 230.67(E) — the minimum stays 10kA regardless of location.
What can connect ahead of the service overcurrent device
NEC 230.94 Only a short, named list of items — surge protection, load management and fire alarm circuits with their own overcurrent protection, meters, and power-operable control circuits — can tap in ahead of the service overcurrent device.
Q28 NEC 230.94
Which of the following is permitted to be connected on the supply side of the service disconnecting means without any condition on separate overcurrent protection?
- A A Type 1 surge-protective device installed per 230.82
- B A power-operable service equipment control circuit
- C A fire pump supply circuit
- D A load management device circuit
Show answer & explanation
Correct: A — A Type 1 surge-protective device installed per 230.82
Per 230.94, surge protection items — including Type 1 SPDs installed as permitted by 230.82 — are permitted on the supply side without the separate-overcurrent-protection condition. Load management circuits, fire pump supply circuits, and power-operable control circuits are all permitted only when given their own overcurrent protection (and, for control circuits, a disconnecting means).
Sizing and ampacity of underground service conductors
NEC 230.31 Underground service conductors follow the same Article 220 load calc as any service, but have their own absolute minimum wire sizes.
Q29 NEC 230.31
An underground service conductor set supplies the general load of a dwelling. Per 230.31(B), what is the smallest permitted aluminum conductor size?
- A 4 AWG aluminum
- B 8 AWG aluminum
- C 6 AWG aluminum
- D 10 AWG aluminum
Show answer & explanation
Correct: C — 6 AWG aluminum
230.31(B) sets the general minimum at 6 AWG aluminum or copper-clad aluminum (8 AWG copper). The 10 AWG aluminum size only applies to the limited single branch-circuit exception, not general service conductors, and 8 AWG and 4 AWG aluminum aren't the stated thresholds.
Clearance near building openings, pools, and communication lines
NEC 230.24(C) 230.24(C), (D), and (E) don't set their own numbers — they point service conductors to the real clearance rules in 230.9(C), 680.9, and 800.44(A)(4).
Q30 NEC 230.24(C) Code lookup
An electrician is routing service-drop conductors past a second-story window that can be opened. Which section sends you to the specific clearance requirements for conductors near a building opening like this?
- A 230.24(C)
- B 230.9
- C 230.24(B)
- D 230.24(A)
Show answer & explanation
Correct: A — 230.24(C)
230.24(C), Clearance from Building Openings, is the specific overhead-service rule that points to 230.9(C) for openable-window clearances. 230.24(A) covers clearance above roofs and 230.24(B) covers vertical clearance over grade/sidewalks/etc., neither of which addresses building openings; 230.9 is the general 'Clearances on Buildings' article referenced by the pointer, not the service clearance section itself covering openings under Part II (Overhead Service Conductors).
Horizontal clearance of open service conductors from windows/doors
NEC 230.9(A) Open service conductors need at least 3 ft of clearance from windows that open, doors, porches, and similar spots — unless they run above the window's top.
Q31 NEC 230.9(A)
Open service conductors are installed near a dwelling. Which location requires at least 900 mm (3 ft) of clearance under 230.9(A)?
- A The roof surface directly below the service drop
- B A window designed to be opened
- C A fixed, non-opening picture window
- D A blank exterior wall with no openings
Show answer & explanation
Correct: B — A window designed to be opened
230.9(A) requires 900 mm (3 ft) clearance from windows designed to be opened, along with doors, porches, balconies, ladders, stairs, and fire escapes. A fixed window that cannot be opened isn't covered by this list, since no one can reach through it toward the conductors.
Individual open conductors entering a building through insulating tubes
NEC 230.52 Individual open service conductors must enter through upward-slanting insulating tubes, with drip loops formed before the tubes.
Q32 NEC 230.52
When individual open conductors enter a building through a wall, how must the insulating tubes be installed?
- A Vertically only, and only when installed with a roof bushing instead
- B Sloped downward toward the interior to shed condensation indoors
- C In an upward slant, with a drip loop formed before the conductors enter
- D Horizontally, packed with duct seal to block moisture
Show answer & explanation
Correct: C — In an upward slant, with a drip loop formed before the conductors enter
230.52 requires individual, noncombustible, nonabsorbent insulating tubes installed in an upward slant, with drip loops formed on the conductors before they enter the tubes. Sloping downward toward the interior would direct water into the building instead of away from it.
One service per building — the general rule
NEC 230.2 A building gets only one service unless it qualifies for one of the four exceptions in 230.2(A) through (D).
Q33 NEC 230.2 Code lookup
A commercial building already has one electric service. The owner wants a second service purely to gain more total ampacity for a planned expansion, with no special occupancy or fire pump involved. Which section lists the conditions under which additional services are permitted for capacity reasons?
- A 230.90
- B 230.2(B)
- C 230.2(A)
- D 230.2(C)
Show answer & explanation
Correct: D — 230.2(C)
230.2(C), Capacity Requirements, is the specific list of conditions allowing a second service when more capacity is needed. 230.2(B) instead covers special occupancies like multiple occupancy buildings, and 230.2(A) covers special conditions like fire pumps and emergency systems, not capacity alone.
Manual/power operation and on-off indication
NEC 230.76 The service disconnect must be hand-operable (or hand-openable during a power failure) and must clearly show open or closed position.
Q34 NEC 230.76 Code lookup
A residential service has a single ungrounded conductor set feeding one main breaker at the meter base. The breaker is motor-operated and controlled remotely by the utility's demand-response system. Which section specifies what must be true about this breaker if utility power to the operator fails?
- A 230.77
- B 230.76
- C 230.74
- D 230.82
Show answer & explanation
Correct: B — 230.76
230.76 requires that a power-operated service disconnect be openable by hand if the power supply to the operator fails. 230.77 only addresses the on/off position indicator, not manual-opening capability, and 230.74 covers simultaneous opening of all poles, not power failure operation.