NEC · 250.122

Equipment Grounding Conductor Sizing (250.122)

The equipment grounding conductor is sized from the overcurrent device, not the circuit conductors — except for the one voltage-drop rule the exam loves to test.

NEC 2017 2020 2023 Last updated 2026-06-26

What the equipment grounding conductor does

The equipment grounding conductor (EGC) is the low-impedance fault-return path. It bonds the non-current-carrying metal parts of an installation — enclosures, raceways, equipment frames — back to the source so that a line-to-ground fault has a deliberate path to clear the overcurrent device quickly. Without an adequate EGC, a fault might leave metal energized instead of tripping the breaker. Sizing it correctly is squarely an Article 250 topic and one of the highest-volume areas on the journeyman exam.

Sizing the EGC from the overcurrent device

The minimum EGC size comes from Table 250.122, and the input is the rating of the overcurrent device ahead of the circuit — not the size of the circuit conductors. A 15-amp circuit needs a 14 AWG copper EGC, a 20-amp circuit needs 12 AWG, a 60-amp circuit needs 10 AWG, a 100-amp circuit needs 8 AWG, and a 200-amp circuit needs 6 AWG copper. Find the breaker or fuse rating, read across, and that is your minimum. The EGC is also never required to be larger than the circuit conductors it runs with, per 250.122(A).

The table value is the minimum only when the ungrounded conductors are no larger than the load and ampacity require. Wire a 20-amp circuit in the 12 AWG the device calls for and the 12 AWG copper EGC from the table stands, with nothing to upsize. But under 250.122(B), the instant those conductors are increased above that required minimum — for any reason, including simply running the heavier wire that happened to be on the truck — the wire-type EGC must be increased in the same proportion. Pull that 20-amp circuit in 10 AWG instead of 12 AWG and the phase conductors grow from about 6,530 to 10,380 circular mils, a factor of roughly 1.59; the 12 AWG EGC (6,530 circular mils) must grow by the same factor, to about 10,380 circular mils — a 10 AWG EGC. The convenience upsize is the textbook case that drags the EGC up right along with it.

The voltage-drop upsize rule

There is one major exception, and it is a classic exam trap. Under 250.122(B), when the ungrounded conductors are increased in size for any reason — most commonly to correct voltage drop on a long run — the equipment grounding conductor must be increased in proportion to the circular-mil area of the ungrounded conductors. In other words, if you upsize the phase conductors, you upsize the EGC by the same ratio.

Worked example: a 40-amp circuit normally takes a 10 AWG copper EGC. To fight voltage drop you increase the phase conductors from 8 AWG to 6 AWG. The circular-mil area grows from about 16,510 to 26,240, a factor of roughly 1.59. Apply that factor to the EGC: 10 AWG is about 10,380 circular mils, and 10,380 × 1.59 ≈ 16,500 circular mils — which rounds up to 8 AWG. The EGC must be upsized to 8 AWG to match the upsized phase conductors.

EGC types and parallel runs

A wire is only one option. Section 250.118 recognizes several wiring methods as equipment grounding conductors — among them rigid metal conduit, intermediate metal conduit, EMT, and the metal armor or sheath of certain cables — so the fault path is not always a green wire. When you do pull a wire-type EGC, it can be copper or aluminum and bare, covered, or insulated.

Parallel circuits are a frequent trap. Where conductors run in parallel in separate raceways, 250.122(F) requires a full-size equipment grounding conductor in each raceway, each sized from the circuit's overcurrent device — not the per-conductor share of the load. Pair that with the rule that an EGC is never required to exceed the circuit conductors, and you have covered the situations the journeyman exam tests most.

Practice questions on this rule

Real journeyman-exam practice questions from Loomi's bank — answer first, then reveal the explanation.

Q1 NEC 250.122(E)

A feeder tap is made downstream of a 400 A overcurrent device. Per 250.122(G), what governs the tap's equipment grounding conductor size?

  1. A Table 250.122 based on the tap's own overcurrent device rating, if the tap has one
  2. B The same size as the tap conductors, regardless of Table 250.122
  3. C Table 250.122 based on the ampacity of the tap conductors themselves
  4. D Table 250.122 based on the 400 A upstream OCPD, but capped at the size of the tap conductors
Show answer & explanation

Correct: D — Table 250.122 based on the 400 A upstream OCPD, but capped at the size of the tap conductors

250.122(G) sizes the tap's EGC from Table 250.122 using the rating of the OCPD ahead of the feeder on the supply side of the tap — here 400 A — but the EGC is never required to be larger than the tap conductors. Sizing from the tap conductors' own ampacity or a downstream device rating misapplies the rule.

Q2 NEC 250.122(A)

Three branch circuits, protected by a 20 A, a 30 A, and a 50 A overcurrent device respectively, are installed in the same cable tray and share a single equipment grounding conductor. How should that EGC be sized per 250.122(C)?

  1. A By averaging the three overcurrent device ratings and using that value in Table 250.122
  2. B From Table 250.122 based on the 20 A overcurrent device, the smallest in the group
  3. C From Table 250.122 based on the 50 A overcurrent device, the largest in the group
  4. D Each circuit needs its own EGC — a shared EGC is not permitted in a cable tray
Show answer & explanation

Correct: C — From Table 250.122 based on the 50 A overcurrent device, the largest in the group

250.122(C) permits a single EGC for multiple circuits in the same raceway, cable, trench, or cable tray, sized from Table 250.122 using the largest overcurrent device protecting any circuit in the group — here, the 50 A device. Sizing off the smallest device or averaging would undersize protection for the larger circuits, and shared EGCs are explicitly allowed in cable trays (subject also to 392.10(B)(1)(c)).

Q3 NEC 250.122(D)

Under 250.122(D)(1), what determines the minimum size of a motor circuit's equipment grounding conductor?

  1. A The motor's nameplate full-load current rating
  2. B The rating of the branch-circuit short-circuit and ground-fault protective device, per 250.122(A)
  3. C The motor's locked-rotor current
  4. D The ampacity of the branch-circuit conductors
Show answer & explanation

Correct: B — The rating of the branch-circuit short-circuit and ground-fault protective device, per 250.122(A)

250.122(D)(1) states the EGC size is not smaller than what 250.122(A) determines based on the branch-circuit short-circuit and ground-fault protective device rating. Motor nameplate current, conductor ampacity, and locked-rotor current are inputs to other motor calculations, not the EGC sizing basis here.

Q4 NEC 250.122(D)

Which overcurrent devices trigger the special EGC sizing rule in 250.122(D)(2) instead of the general rule in 250.122(D)(1)?

  1. A Instantaneous-trip circuit breakers and motor short-circuit protectors
  2. B Dual element time-delay fuses only
  3. C Standard inverse-time circuit breakers only
  4. D Any overcurrent device serving a motor circuit over 100 A
Show answer & explanation

Correct: A — Instantaneous-trip circuit breakers and motor short-circuit protectors

250.122(D)(2) applies specifically when the overcurrent device is an instantaneous-trip circuit breaker or a motor short-circuit protector. Standard breakers and fuses fall under the general method in 250.122(D)(1); device size threshold (like 100 A) isn't the trigger.

All Grounding and Bonding practice questions (Article 250)

Frequently asked questions

What determines the size of the equipment grounding conductor?
The rating of the overcurrent device protecting the circuit, read from Table 250.122 — not the size of the circuit conductors. A 20-amp breaker calls for a 12 AWG copper EGC, a 100-amp device for 8 AWG, and a 200-amp device for 6 AWG copper.
Do you have to upsize the ground wire when you upsize the conductors?
Only when the ungrounded conductors are increased in size, for example to correct voltage drop. Under 250.122(B), the EGC must then be increased in proportion to the circular-mil increase of the ungrounded conductors.
Is the EGC ever required to be larger than the circuit conductors?
No. Section 250.122(A) states the equipment grounding conductor is not required to be larger than the circuit conductors supplying the equipment, even when a table value would otherwise suggest it.
Loomi · NEC exam prep

Practice the NEC concepts in this article.

Loomi turns NEC content into 12,934 spaced-repetition exam questions built for the journeyman test. Try everything free for 3 days.

Get launch access