Free NEC practice test · Article 300

Wiring Methods practice questions

A free NEC Article 300 practice test for the journeyman exam: 25 questions on General Requirements for Wiring Methods and Materials, each with the answer and the why behind it.

25 questions · free · answers included NEC 2023 · Updated

How to use this practice test

These 25 journeyman-exam practice questions cover NEC Article 300 across 25 code concepts, every one with the correct answer and a plain-English explanation of the rule behind it. They come from the same question bank the Loomi app trains you on — this is the free web sample, not a separate watered-down set.

Work straight down the sheet and answer before you peek: each question hides its answer behind Show answer & explanation. Questions tagged Code lookup are speed drills — race your codebook to the cited section. Printing this page gives you a clean paper worksheet with the answers left off.

Protecting Cables and Raceways from Nails and Screws

NEC 300.4(A)

Keep cables and raceways at least 1-1/4 in. from the framing edge; if you can't, cover them with a 1/16-in. steel plate.

Q1 NEC 300.4(A)

A romex cable is run through a bored hole in a wood stud, and only 3/4 in. of clearance can be maintained to the edge of the stud. What does 300.4(A)(1) require?

  1. A Switching to rigid nonmetallic conduit, which has no clearance or plate requirement
  2. B Nothing further, since 3/4 in. is enough clearance for cable-type wiring methods
  3. C Re-boring the hole so the cable is centered in the stud
  4. D A steel plate or bushing at least 1/16 in. thick covering the area of the wiring
Show answer & explanation

Correct: D — A steel plate or bushing at least 1/16 in. thick covering the area of the wiring

300.4(A)(1) requires 1-1/4 in. (32 mm) of edge clearance in bored holes; when that can't be maintained, a steel plate or bushing at least 1/16 in. thick must cover the wiring area. Rigid nonmetallic conduit is exempt from the plate requirement, but it still must meet or be protected per the same clearance logic — it isn't a free pass with zero clearance consideration, and simply re-centering the hole doesn't satisfy the rule unless it achieves the 1-1/4 in. distance.

Keep All Conductors of a Circuit in the Same Raceway or Cable

NEC 300.3(B)

Every conductor of a circuit — hot, neutral, and equipment grounding conductor — must run together in the same raceway or cable, with only a few narrow exceptions.

Q2 NEC 300.3(B)

Per 300.3(B), which of the following must be installed in the same raceway or cable as the ungrounded conductors of a circuit?

  1. A Nothing else is required to share the raceway as long as conduit fill is met
  2. B Only the equipment grounding conductor, since the grounded conductor may run separately
  3. C The grounded conductor and all equipment grounding and bonding conductors, where used
  4. D Only the ungrounded conductors of other unrelated circuits sharing the panel
Show answer & explanation

Correct: C — The grounded conductor and all equipment grounding and bonding conductors, where used

300.3(B) requires all conductors of the same circuit — the grounded conductor and any equipment grounding or bonding conductors used — to be in the same raceway, cable, tray, gutter, trench, or cord. Believing the grounded conductor can run separately, or that only conduit fill matters, ignores the induction-heating hazard this rule prevents.

Protecting Underground Conductors at Grade and Entry Points

NEC 300.5(D)

Direct-buried conductors need a raceway or enclosure wherever they rise out of the ground, enter a building, or sit somewhere they can get hit.

Q3 NEC 300.5(D)

Direct-buried conductors emerge from grade and rise up the side of a pole. Per 300.5(D)(1), what is the required minimum height of protection above finished grade?

  1. A 1.8 m (6 ft)
  2. B 450 mm (18 in.)
  3. C 2.5 m (8 ft)
  4. D 3.0 m (10 ft)
Show answer & explanation

Correct: C — 2.5 m (8 ft)

300.5(D)(1) requires protection to extend to at least 2.5 m (8 ft) above finished grade. The 450 mm (18 in.) figure is the maximum depth the protection must extend below grade, not the height above it, and 1.8 m and 3.0 m are not the code-specified values.

Box Not Required When Equipment Itself Provides the Enclosure

NEC 300.15(A)

A separate box isn't required at a splice, switch, or termination point if the equipment itself already provides an accessible enclosure — a wireway cover, an integral wiring compartment, a cabinet, or a listed luminaire-as-raceway.

Q4 NEC 300.15(A) Code lookup

A packaged HVAC unit has a factory-installed wiring compartment for making the field splices to the branch-circuit conductors. Which section permits omitting a separate junction box because the equipment's integral compartment serves that purpose?

  1. A 300.15(A)
  2. B 300.15(I)
  3. C 300.15(B)
  4. D 300.15(J)
Show answer & explanation

Correct: C — 300.15(B)

300.15(B) permits an integral junction box or wiring compartment that is part of approved equipment to serve in lieu of a separate box. 300.15(I) instead covers splices made inside cabinets, cutout boxes, or switch/OCPD enclosures per 312.8, not equipment's own built-in compartment, and 300.15(A) applies only to wiring methods with removable covers like wireways.

Conductor Continuity — No In-Raceway Splices & Multiwire Neutral Rule

NEC 300.13(A)

Never splice inside a raceway unless a specific exception allows it, and never let a multiwire circuit's neutral depend on a device to stay continuous.

Q5 NEC 300.13(A)

An electrician wants to join two conductors together with a wire nut inside a straight run of EMT conduit, with no box at that point. Is this permitted?

  1. A Yes, as long as the conduit is accessible for future maintenance
  2. B No, splices within a raceway are not permitted unless specifically allowed by a section like 300.15
  3. C No, but only because EMT specifically prohibits it — other raceway types allow it
  4. D Yes, as long as the wire nut is rated for the conductor size
Show answer & explanation

Correct: B — No, splices within a raceway are not permitted unless specifically allowed by a section like 300.15

300.13(A) requires conductors in raceways to be continuous between outlets and boxes, with no splice or tap within the raceway unless permitted by 300.15 or another cited section. Accessibility and wire nut rating don't create an exception, and the rule applies to raceways generally, not just EMT.

Conduit Fill (NEC Chapter 9)

NEC 300.17

For more than two conductors, fill is limited to 40% of the raceway's internal area (Chapter 9, Table 1). Sum the conductor areas (Table 5) and pick the smallest raceway whose 40% area (Table 4) covers the total.

Q6 NEC 300.17

What is the minimum size EMT required for 10 THHN 12 AWG conductors? (NEC Chapter 9 fill)

  1. A 3/4" EMT
  2. B 1/2" EMT
  3. C 1" EMT
  4. D 1-1/4" EMT
Show answer & explanation

Correct: A — 3/4" EMT

Each 12 AWG THHN is 0.0133 in² (Table 5), so 10 conductors need 10 × 0.0133 = 0.133 in². With more than two conductors the fill limit is 40% (Table 1), and Table 4 lists each EMT's 40% area — the smallest whose 40% area reaches 0.133 in² is 3/4" EMT. Distractors are one trade size off.

Direct-Burial Details — Splices, Backfill, Seals & Bushings

NEC 300.5(E)

Direct-buried conductors can be spliced without a box, but backfill must be clean, raceways sealed against moisture, and every underground raceway end bushed.

Q7 NEC 300.5(E) Code lookup

An electrician is direct-burying two conductors and needs to make a splice underground. The AHJ asks whether an underground splice box is required at that point. Which section addresses splicing or tapping direct-buried conductors without a splice box?

  1. A 300.5(H)
  2. B 300.5(F)
  3. C 300.5(E)
  4. D 300.5(I)
Show answer & explanation

Correct: C — 300.5(E)

300.5(E) permits direct-buried conductors or cables to be spliced or tapped without a splice box, provided the splice meets 110.14(B). 300.5(F) covers backfill material instead, and 300.5(I) addresses keeping same-circuit conductors grouped, not splicing.

Wiring Methods Permitted in Fabricated Environmental Air Ducts

NEC 300.22(B)

Only rigid, metal-jacketed wiring methods like MI cable, MC cable, EMT, IMC, or RMC can run inside a fabricated environmental air duct, and only to serve equipment that acts on the air itself.

Q8 NEC 300.22(B)

Which wiring method is permitted for general installation inside a duct specifically fabricated for environmental air?

  1. A Type MC cable with an overall nonmetallic covering
  2. B Type NM cable
  3. C Rigid metal conduit without an overall nonmetallic covering
  4. D Electrical nonmetallic tubing (ENT)
Show answer & explanation

Correct: C — Rigid metal conduit without an overall nonmetallic covering

300.22(B) permits Type MI cable, Type MC cable with a smooth or corrugated impervious metal sheath, EMT, flexible metallic tubing, IMC, or RMC — all without an overall nonmetallic covering. ENT, MC cable with a nonmetallic jacket, and NM cable are not on this list because their outer coverings or construction aren't suited to the airstream and fire-safety demands of a fabricated air duct.

Corrosion Protection for Ferrous Metal Raceways and Equipment

NEC 300.6(A)

Ferrous metal raceways and enclosures need corrosion protection inside and out, but enamel alone isn't enough outdoors or in wet locations.

Q9 NEC 300.6(A) Code lookup

An electrician is installing rigid ferrous metal conduit that will be encased directly in a concrete foundation footing. What condition must be met for this ferrous raceway to be installed under these severely corrosive conditions?

  1. A 300.6(B)
  2. B 300.6(A)
  3. C 300.6(A)(3)
  4. D 300.5(D)(4)
Show answer & explanation

Correct: C — 300.6(A)(3)

300.6(A)(3) specifically addresses ferrous metal raceways installed in concrete or in direct contact with earth, requiring material approved for the condition or added corrosion protection. 300.6(A) is the general ferrous coating rule (not the concrete/earth exception), 300.5(D)(4) covers physical damage protection for underground enclosures/raceways rather than corrosion, and 300.6(B) applies to aluminum, not ferrous, equipment.

Firestopping Electrical Penetrations Through Rated Assemblies

NEC 300.21

Any opening made for a electrical penetration through a fire-rated wall, floor, or ceiling must be firestopped to restore that assembly's original fire-resistance rating.

Q10 NEC 300.21

An electrician runs conduit through a 2-hour fire-rated corridor wall in a commercial building. Per 300.21, what is required at the penetration?

  1. A No action is needed as long as the conduit itself is metallic
  2. B The opening only needs firestopping if it exceeds 6 in. in diameter
  3. C The opening must be firestopped with approved methods to maintain the wall's fire resistance rating
  4. D Firestopping is only required for penetrations through floors, not walls
Show answer & explanation

Correct: C — The opening must be firestopped with approved methods to maintain the wall's fire resistance rating

300.21 requires firestopping at any opening around an electrical penetration into or through a fire-resistance-rated wall, partition, floor, or ceiling, regardless of the conduit material, opening size, or whether it's a wall or floor — those are all plausible-sounding but incorrect limitations not found in the rule.

Wiring, Cable Trays, and Equipment in Other Plenum Spaces

NEC 300.22(C)

In a space not built for air handling but used as one anyway — like above a hung ceiling — wiring is limited to low-combustion cables or metal raceway, and equipment needs a metal or listed low-smoke enclosure.

Q11 NEC 300.22(C)

Which cable is permitted to be installed in an other space used as an environmental air plenum, such as above a hung ceiling?

  1. A Type MC cable with an overall nonmetallic covering
  2. B PVC (nonmetallic) conduit enclosing standard building wire
  3. C Type MC cable without an overall nonmetallic covering
  4. D Type NM (nonmetallic-sheathed) cable
Show answer & explanation

Correct: C — Type MC cable without an overall nonmetallic covering

300.22(C)(1) permits Type MC cable only without an overall nonmetallic covering. Adding a nonmetallic jacket, using Type NM cable, or running wiring in nonmetallic PVC conduit are not on the permitted list — only metal raceways like EMT, IMC, RMC, or FMC may enclose other wiring types.

Securing Wiring in Place & Using Raceways (Not Cables) as Support

NEC 300.11(A)

Raceways, cables, boxes, and fittings must be securely fastened in place, and only raceways — never cables — can serve as support for other wiring, subject to narrow exceptions.

Q12 NEC 300.11(A)

An installer wants to hang a length of EMT from an existing NM cable run to keep it out of the way. Is this permitted?

  1. A No, cable wiring methods shall not be used as a means of support for other raceways
  2. B Yes, as long as the EMT is lightweight
  3. C Yes, if the cable is rated for the additional load
  4. D Yes, if the span is under 3 feet
Show answer & explanation

Correct: A — No, cable wiring methods shall not be used as a means of support for other raceways

Per 300.11(D), cable wiring methods shall not be used as a means of support for other cables, raceways, or nonelectrical equipment, regardless of weight, rating, or span. There is no cable-load or short-span exception. Weight, rating, and span are all invented conditions.

Supporting Wiring Above Suspended Ceilings

NEC 300.11(B)

Ceiling grids and their support wires can never be the sole support for cables or raceways — you need independent support wires, secured at both ends and identifiable.

Q13 NEC 300.11(B)

An electrician wants to support MC cable above a suspended ceiling using extra wires run alongside the ceiling grid's own support wires. Under 300.11(B), what must be true of these extra wires?

  1. A They only need to be secured at one end since the grid wires provide backup support
  2. B They must be secured at both ends
  3. C They are not needed if the grid wires are rated for the ceiling tile weight
  4. D They must be the same wires used to support the ceiling grid
Show answer & explanation

Correct: B — They must be secured at both ends

300.11(B) requires that where independent support wires are used, they be secured at both ends. Ceiling grid support wires — even if adequate for the tiles — cannot be the sole support for cables, so one-end securing or relying on the grid wires alone does not satisfy the rule.

Underground Circuit Grouping, Earth Movement & Directional Boring

NEC 300.5(I)

Keep all conductors of a circuit together in the same raceway, cable, or trench; leave slack for ground movement; and use listed-for-the-purpose cable or raceway for directional boring.

Q14 NEC 300.5(I) Code lookup

A crew is direct-burying a 3-phase feeder as three single-conductor cables plus an equipment grounding conductor, run in parallel sets, from a pad-mount transformer to a building. Which section specifies how these single conductors must be positioned relative to each other in the trench?

  1. A 300.5(I)
  2. B 300.5(D)(4)
  3. C 300.5(A)
  4. D 300.5(F)
Show answer & explanation

Correct: A — 300.5(I)

300.5(I) requires that conductors of the same circuit, including parallel single-conductor direct-buried cables and their equipment grounding conductors, be installed in close proximity within the same trench. 300.5(F) governs backfill material and 300.5(A) sets cover depth, neither addresses conductor grouping.

Supporting Conductors in Vertical Raceways

NEC 300.19(A)

Conductors in a vertical raceway need support once the rise exceeds the spacing in Table 300.19(A), with a support at the top and intermediate supports below.

Q15 NEC 300.19(A)

Under 300.19(A), where must at least one support method be provided for conductors in a vertical raceway?

  1. A Only where the raceway penetrates a fire-rated wall
  2. B At the midpoint of the total rise
  3. C At the top of the raceway, or as close to the top as practical
  4. D At the bottom of the raceway only
Show answer & explanation

Correct: C — At the top of the raceway, or as close to the top as practical

300.19(A) requires at least one support method at the top of the vertical raceway, or as close to the top as practical, with intermediate supports added as needed to limit conductor lengths. Bottom-only or midpoint support does not satisfy this, and fire-wall penetration isn't the trigger for support placement.

Corrosion Protection for Aluminum and Nonmetallic Equipment

NEC 300.6(B)

Aluminum equipment embedded in concrete or earth needs supplementary corrosion protection; nonmetallic equipment must be sunlight-resistant and chemical-resistant where exposed.

Q16 NEC 300.6(B)

An aluminum auxiliary gutter is installed encased in concrete below grade. What does the NEC require?

  1. A No additional protection, since aluminum does not corrode in concrete
  2. B A listing as sunlight resistant
  3. C Identification for the specific chemical reagent present in the soil
  4. D Supplementary corrosion protection
Show answer & explanation

Correct: D — Supplementary corrosion protection

Per 300.6(B), aluminum equipment embedded in concrete or in direct contact with earth must have supplementary corrosion protection. Sunlight-resistant listing and chemical-reagent identification are 300.6(C) requirements for nonmetallic equipment, not aluminum, and aluminum does in fact react with concrete's alkalinity and soil moisture.

Box Not Required — Protective Fittings and NM Cable Devices

NEC 300.15(C)

A box is only skipped when a listed fitting or integral-enclosure device does the job instead — and if conductors get spliced or terminated inside, a box is back on the table.

Q17 NEC 300.15(C)

An electrician wants to install a listed fitting in lieu of a box where two NM cables meet inside a wall cavity, with the conductors spliced together inside the fitting. Is this permitted under 300.15(F)?

  1. A Yes, as long as the fitting is listed for concealed installation
  2. B No, because fittings can never be used in concealed locations
  3. C Yes, as long as the fitting is accessible after installation
  4. D No, because 300.15(F) only applies when conductors are not spliced or terminated within the fitting
Show answer & explanation

Correct: D — No, because 300.15(F) only applies when conductors are not spliced or terminated within the fitting

300.15(F) allows a fitting identified for the use in lieu of a box only where conductors are NOT spliced or terminated within the fitting. Accessibility (or a concealed-installation listing) is a separate requirement that applies once that no-splice condition is already met — it doesn't override it. Fittings can be used concealed if listed for it, so that option is also wrong.

Box Not Required — Direct Burial, Embedded, and Manhole Installations

NEC 300.15(G)

Splices don't need a box when they're direct-buried, embedded in listed heating equipment, or in a manhole/handhole not connecting to equipment.

Q18 NEC 300.15(G) Code lookup

An electrician is direct-burying a set of feeder conductors in the ground between a house and a detached garage, per 300.5(E), and needs to make a splice in the run underground without installing a box. Which section confirms that a box or conduit body is not required for this splice?

  1. A 300.15(L)
  2. B 300.15(E)
  3. C 300.15(G)
  4. D 300.15(K)
Show answer & explanation

Correct: C — 300.15(G)

300.15(G) specifically exempts direct-buried conductors and cables from the box/conduit body requirement for splices and taps, cross-referencing 300.5(E). 300.15(K) covers embedded conductors (e.g., in concrete floor heating), and 300.15(L) covers manholes/handholes — neither applies to a direct-buried underground run.

Protecting Large Conductors Entering Enclosures

NEC 300.4(G)

4 AWG and larger insulated conductors need a smooth, rounded insulating protection at every raceway entry into a box or enclosure — bare metal edges aren't enough.

Q19 NEC 300.4(G)

An electrician is running 2 AWG THHN conductors through rigid metal conduit into a panelboard enclosure. Per 300.4(G), what must be done at the raceway entry?

  1. A An all-insulating conduit bushing alone must be installed to both protect and secure the raceway
  2. B Nothing extra is required because 2 AWG conductors are exempt from the fitting requirement
  3. C The conductors must be protected with an identified insulating fitting, a listed rounded-edge metal fitting, secured insulating material, or an integral rounded/flared hub
  4. D A standard locknut and non-insulated bushing is sufficient regardless of conductor size
Show answer & explanation

Correct: C — The conductors must be protected with an identified insulating fitting, a listed rounded-edge metal fitting, secured insulating material, or an integral rounded/flared hub

300.4(G) applies to insulated conductors 4 AWG and larger, so 2 AWG THHN triggers the requirement — one of the listed protection methods (insulating fitting, rounded metal fitting, secured insulating material, or integral flared hub) must be used. It is not exempt, a plain non-insulated bushing does not satisfy the rounded-surface requirement, and an all-insulating bushing cannot serve as the securing means per 300.4(G).

Mixing Different Voltage-Class Circuits in One Enclosure

NEC 300.3(C)

At or below 1000V ac/1500V dc, different-voltage circuits can share an enclosure if every conductor is insulated for the highest voltage present; above that line, mixing is barred unless 305.4 allows it.

Q20 NEC 300.3(C)

A 208-volt branch circuit and a 480-volt branch circuit are installed together in the same raceway. Per 300.3(C)(1), what must be true?

  1. A The 208-volt conductors must be upsized to match the 480-volt conductors' ampacity
  2. B Every conductor in the raceway must be insulated for at least 480 volts
  3. C The two circuits must be separated by a raceway divider
  4. D Each voltage class needs its own dedicated raceway
Show answer & explanation

Correct: B — Every conductor in the raceway must be insulated for at least 480 volts

300.3(C)(1) permits conductors of ac/dc circuits rated 1000 volts ac, 1500 volts dc, or less to share a raceway as long as every conductor's insulation rating is at least equal to the highest circuit voltage present — here, 480 volts. There's no requirement for a physical divider, separate raceways, or ampacity matching between the two circuits; those confuse this section with conduit-fill or overcurrent rules.

Airspace Clearance in Indoor Wet/Corrosive Locations

NEC 300.6(D)

Exposed wiring in indoor wet or corrosive locations needs a 6 mm airspace off the wall, unless it's a nonmetallic raceway, box, or fitting on concrete, masonry, or tile.

Q21 NEC 300.6(D)

In a dairy processing facility with exposed metal conduit mounted on a wall, what airspace must be maintained between the conduit and the wall per 300.6(D)?

  1. A At least 6 mm (1/4 in.)
  2. B No airspace is required if the conduit is rigid metal
  3. C At least 25 mm (1 in.)
  4. D Airspace is only required if the wall is wood
Show answer & explanation

Correct: A — At least 6 mm (1/4 in.)

300.6(D) requires at least a 6 mm (1/4 in.) airspace between exposed wiring systems and the wall or supporting surface in indoor wet locations like dairy processing facilities. The 'no airspace for metal conduit' and 'wood wall only' options misread the rule — it applies to the entire exposed wiring system regardless of raceway type, and the 25 mm figure is not the code minimum.

Preventing Inductive Heating in Ferrous Metal Enclosures

NEC 300.20(A)

AC conductors in ferrous metal must keep all phase, neutral, and ground conductors together in the same enclosure so the magnetic field cancels out instead of heating the metal.

Q22 NEC 300.20(A)

A feeder with three phase conductors, a neutral, and an equipment grounding conductor runs through a steel enclosure. Per 300.20(A), how must these conductors be arranged?

  1. A Each phase conductor in its own individual steel raceway
  2. B The equipment grounding conductor run in a separate steel raceway for isolation
  3. C All grouped together in the same enclosure
  4. D Phase conductors grouped, with the neutral routed through a different knockout
Show answer & explanation

Correct: C — All grouped together in the same enclosure

300.20(A) requires all phase conductors, the grounded conductor, and equipment grounding conductors to be grouped together to cancel the magnetic field and avoid inductive heating of the ferrous metal. Separating any of them into their own raceway or knockout — including the equipment grounding conductor except under the narrow existing-installation allowance in 250.130(C) — defeats the cancellation and is the wrong approach.

Electrical Continuity of Metal Raceways and Enclosures

NEC 300.10

Metal raceways, cable armor, and enclosures must be joined into one continuous electrical path, with two narrow exceptions for physical-protection sleeves and isolated grounding enclosures.

Q23 NEC 300.10 Code lookup

A contractor is installing a metal conduit run to feed a panel and needs to know the rule requiring that raceway to be metallically joined and mechanically secured to every box, fitting, and cabinet along the run so the whole system acts as one continuous grounding path. Which section covers this requirement?

  1. A 300.10
  2. B 300.13
  3. C 300.11
  4. D 300.12
Show answer & explanation

Correct: A — 300.10

300.10 requires metal raceways, cable armor, and enclosures to be metallically joined into a continuous conductor and mechanically secured to boxes, fittings, and cabinets. 300.12 instead addresses mechanical continuity of raceways and cables at joints/couplings, and 300.11 covers securing/supporting raceways generally, not electrical continuity.

Non-Power-Limited Remote-Control Circuit Sizing and Protection

NEC 300.26(C)

Non-power-limited remote-control and signaling circuits follow full Chapter 3 wiring rules, plus their own conductor size, insulation, and overcurrent limits.

Q24 NEC 300.26(C)

A non-power-limited remote-control circuit uses 18 AWG copper conductors. What is the maximum overcurrent protection allowed, absent another Code rule requiring or permitting a different rating?

  1. A 15 amperes
  2. B 10 amperes
  3. C 7 amperes
  4. D 20 amperes
Show answer & explanation

Correct: C — 7 amperes

300.26(C)(3)(b) caps overcurrent protection at 7 amperes for 18 AWG copper conductors. The 10-ampere figure applies instead to 16 AWG copper or 14 AWG copper-clad aluminum conductors, and 15 and 20 amperes are standard branch-circuit ratings that don't apply here.

Raceways Installed Complete Before Wiring; No Welding for Support

NEC 300.18(A)

Pull raceways together fully before pulling wire, and never weld a metal raceway to support, terminate, or connect it.

Q25 NEC 300.18(A) Code lookup

A crew is pulling THHN conductors into a run of EMT between two junction boxes on a commercial job. The raceway itself hasn't been fully assembled yet between those points. Which section requires the raceway to be installed complete between outlet, junction, or splicing points before conductors are pulled in?

  1. A 300.19(C)
  2. B 300.18(A)
  3. C 300.17
  4. D 300.15(A)
Show answer & explanation

Correct: B — 300.18(A)

300.18(A) is the specific rule requiring raceways to be installed complete between termination points before conductors are pulled in. 300.17 instead governs how many conductors/cables are permitted in a raceway based on fill, not sequencing of installation.

Loomi · NEC exam prep

2,035 questions free on the web. 12,934 in the app.

Loomi's full journeyman bank is timed, NEC-referenced, and runs on spaced repetition that hammers what you miss. Try everything free for 3 days.

Get launch access